21-00020-00-BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $535,667 | ||
| 2 | Gillan Construction LLC | $561,554 | +4.8% | |
| 3 | Riber Construction, Inc. | $651,667 | +21.7% | |
| 4 | Tobey's Construction & Cartage, Inc. | $690,114 | +28.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Gillan Construc… | #3 Riber Construct… | #4 Tobey's Constru… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X5110304 | SLOPE WALL SPECIAL | 28 | SQ YD | $100.00 | $175.00 | $190.00 | $215.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $11,500.00 | $10,000.00 | $4,725.00 | $4,725.00 | |
| 3 | X7200061 | TEMP INFO SIGNING | 42 | SQ FT | $25.00 | $25.00 | $25.00 | $25.00 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $5,000.00 | $5,000.00 | $3,000.00 | |
| 5 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 7 | 20400800 | FURNISHED EXCAVATION | 144 | CU YD | $40.00 | $50.00 | $100.00 | $43.00 | |
| 8 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $869.00 | $15,400.00 | $3,160.00 | $3,160.00 | |
| 9 | 25000400 | NITROGEN FERT NUTR | 22 | POUND | $11.00 | $5.50 | $10.00 | $10.00 | |
| 10 | 25000500 | PHOSPHORUS FERT NUTR | 22 | POUND | $11.00 | $5.50 | $10.00 | $10.00 | |
| 11 | 25000600 | POTASSIUM FERT NUTR | 22 | POUND | $11.00 | $5.50 | $10.00 | $10.00 | |
| 12 | 25100630 | EROSION CONTR BLANKET | 50 | SQ YD | $11.00 | $11.00 | $10.00 | $10.00 | |
| 13 | 28100107 | STONE RIPRAP CL A4 | 44 | SQ YD | $100.00 | $80.00 | $90.00 | $132.00 | |
| 14 | 28200200 | FILTER FABRIC | 44 | SQ YD | $10.00 | $3.00 | $2.50 | $3.00 | |
| 15 | 35101400 | AGG BASE CSE B | 16 | TON | $50.00 | $42.50 | $80.00 | $120.00 | |
| 16 | 40600275 | BIT MATLS PR CT | 79 | POUND | $0.0100 | $1.00 | $0.0100 | $0.0100 | |
| 17 | 40600290 | BIT MATLS TACK CT | 90 | POUND | $0.0100 | $1.00 | $0.0100 | $0.0100 | |
| 18 | 40603080 | HMA BC IL-19.0 N50 | 10 | TON | $500.00 | $350.00 | $500.00 | $725.00 | |
| 19 | 40603200 | P HMA BC IL-4.75 N50 | 1 | TON | $1,000.00 | $350.00 | $1,000.00 | $1,500.00 | |
| 20 | 40604050 | HMA SC IL-9.5 C N50 | 36 | TON | $200.00 | $350.00 | $200.00 | $400.00 | |
| 21 | 44000100 | PAVEMENT REM | 88 | SQ YD | $25.00 | $70.00 | $110.00 | $70.00 | |
| 22 | 44000155 | HMA SURF REM 1 1/2 | 149 | SQ YD | $18.00 | $35.00 | $18.00 | $48.00 | |
| 23 | 48101200 | AGGREGATE SHLDS B | 7 | TON | $100.00 | $75.00 | $103.00 | $190.00 | |
| 24 | 50100100 | REM EXIST STRUCT | 1 | EACH | $20,000.00 | $29,000.00 | $67,300.00 | $72,000.00 | |
| 25 | 50200100 | STRUCTURE EXCAVATION | 374 | CU YD | $30.00 | $30.00 | $30.00 | $50.00 | |
| 26 | 50300225 | CONC STRUCT | 28.7 | CU YD | $900.00 | $1,100.00 | $1,600.00 | $1,750.00 | |
| 27 | 50300280 | CONCRETE ENCASEMENT | 2.1 | CU YD | $1,000.00 | $1,000.00 | $1,800.00 | $2,300.00 | |
| 28 | 50400605 | P P CONC DK BM 33 DP | 1,876 | SQ FT | $109.50 | $110.00 | $120.00 | $135.25 | |
| 29 | 50800205 | REINF BARS, EPOXY CTD | 3,140 | POUND | $3.00 | $2.50 | $3.00 | $3.25 | |
| 30 | 50901050 | STEEL RAILING TY SM | 176 | FOOT | $238.70 | $264.00 | $281.00 | $240.00 | |
| 31 | 51201400 | FUR STL PILE HP10X42 | 500 | FOOT | $113.61 | $80.00 | $136.00 | $81.00 | |
| 32 | 51202305 | DRIVING PILES | 500 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 33 | 51204650 | PILE SHOES | 13 | EACH | $200.00 | $175.00 | $95.00 | $200.00 | |
| 34 | 51500100 | NAME PLATES | 1 | EACH | $1,400.00 | $1,100.00 | $650.00 | $900.00 | |
| 35 | 58100210 | FLS WATERPROOF SYSTEM | 208 | SQ YD | $113.00 | $128.00 | $113.00 | $160.00 | |
| 36 | 58300100 | PC MORTAR FAIRING CSE | 402 | FOOT | $7.00 | $25.00 | $0.0100 | $2.00 | |
| 37 | 58600101 | GRANULAR BACKFILL STR | 26 | CU YD | $65.00 | $60.00 | $60.00 | $145.00 | |
| 38 | 63100087 | TRAF BAR TERM T6A | 4 | EACH | $5,060.00 | $5,060.00 | $3,695.00 | $4,600.00 | |
| 39 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,850.00 | $3,850.00 | $4,225.00 | $3,500.00 | |
| 40 | 63200310 | GUARDRAIL REMOV | 430 | FOOT | $9.90 | $5.00 | $5.00 | $9.00 | |
| 41 | 67100100 | MOBILIZATION | 1 | L SUM | $22,100.00 | $30,000.00 | $35,000.00 | $40,000.00 | |
| 42 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $44.00 | $44.00 | $50.00 | $40.00 | |
| 43 | 78001110 | PAINT PVT MK LINE 4 | 1,364 | FOOT | $2.64 | $2.64 | $2.40 | $2.40 | |
| 44 | 78200006 | GRDRAIL REF TYPE B | 6 | EACH | $24.20 | $24.20 | $35.00 | $22.00 |