20-00199-04-BR
- Let date
- Friday, April 26, 2024
- Contract
- 87820 · job page
- District
- District 3
- County
- Livingston
- Highway
- Limits
- Replace existng structure with a three-span RC slab bridge with HMA approach, aggregate and HMA shoulders, and guardrail improvements on CH 3 over Broughton Creek, one mile north of Campus.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Tobey's Construction & Cartage, Inc. Low bidder | $737,652 | ||
| 2 | Riber Construction, Inc. | $754,724 | +2.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Tobey's Constru… | #2 Riber Construct… |
|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.4 | ACRE | $9,450.00 | $9,450.00 | |
| 2 | 20200100 | EARTH EXCAVATION | 485 | CU YD | $33.00 | $60.00 | |
| 3 | 20300100 | CHANNEL EXCAVATION | 130 | CU YD | $22.00 | $60.00 | |
| 4 | 20700110 | POROUS GRAN EMBANK | 95 | TON | $28.00 | $28.00 | |
| 5 | 28100107 | STONE RIPRAP CL A4 | 620 | SQ YD | $66.00 | $63.00 | |
| 6 | 28200200 | FILTER FABRIC | 620 | SQ YD | $1.15 | $2.00 | |
| 7 | 35101400 | AGG BASE CSE B | 478 | TON | $34.00 | $23.00 | |
| 8 | 40600275 | BIT MATLS PR CT | 3,021 | POUND | $0.8500 | $0.8500 | |
| 9 | 40600290 | BIT MATLS TACK CT | 501 | POUND | $0.0100 | $0.0100 | |
| 10 | 40603080 | HMA BC IL-19.0 N50 | 291 | TON | $117.00 | $117.00 | |
| 11 | 40604050 | HMA SC IL-9.5 C N50 | 120 | TON | $118.00 | $118.00 | |
| 12 | 48101200 | AGGREGATE SHLDS B | 40 | TON | $39.00 | $50.00 | |
| 13 | 50100100 | REM EXIST STRUCT | 1 | EACH | $30,000.00 | $46,000.00 | |
| 14 | 50200100 | STRUCTURE EXCAVATION | 80 | CU YD | $20.00 | $35.00 | |
| 15 | 50300225 | CONC STRUCT | 46.4 | CU YD | $1,095.00 | $1,200.00 | |
| 16 | 50300255 | CONC SUP-STR | 142.4 | CU YD | $1,410.00 | $1,075.00 | |
| 17 | 50300260 | BR DECK GROOVING | 316 | SQ YD | $14.80 | $20.00 | |
| 18 | 50300280 | CONCRETE ENCASEMENT | 25.2 | CU YD | $1,100.00 | $1,500.00 | |
| 19 | 50300300 | PROTECTIVE COAT | 369 | SQ YD | $2.30 | $2.50 | |
| 20 | 50800205 | REINF BARS, EPOXY CTD | 60,340 | POUND | $1.62 | $1.70 | |
| 21 | 50900209 | STEEL RAILING TY SMX | 177 | FOOT | $263.28 | $263.28 | |
| 22 | 51200957 | FUR M S PILE 12X0.250 | 765 | FOOT | $74.00 | $40.00 | |
| 23 | 51202305 | DRIVING PILES | 765 | FOOT | $0.0100 | $0.0100 | |
| 24 | 51203200 | TEST PILE MET SHELLS | 2 | EACH | $3,800.00 | $24,000.00 | |
| 25 | 51500100 | NAME PLATES | 1 | EACH | $450.00 | $535.00 | |
| 26 | 63100087 | TRAF BAR TERM T6A | 4 | EACH | $4,663.20 | $4,663.20 | |
| 27 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,420.00 | $3,420.00 | |
| 28 | 63200310 | GUARDRAIL REMOV | 734 | FOOT | $5.63 | $5.25 | |
| 29 | 67100100 | MOBILIZATION | 1 | L SUM | $40,000.00 | $40,000.00 | |
| 30 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $35.00 | $35.00 | |
| 31 | 78200005 | GRDRAIL REF TYPE A | 6 | EACH | $10.00 | $10.00 |