22-00283-00-BR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sjostrom & Sons, Inc. Low bidder | $436,742 | ||
| 2 | D. Construction, Inc. | $447,699 | +2.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sjostrom & Sons… | #2 D. Construction… |
|---|---|---|---|---|---|---|---|
| 1 | X2020410 | EARTH EXCAVATION SPL | 203 | CU YD | $77.00 | $50.00 | |
| 2 | X2070302 | POROUS GRAN EMB SPEC | 376 | TON | $45.00 | $40.00 | |
| 3 | X2501000 | SEEDING CL 2 SPL | 0.3 | ACRE | $11,500.00 | $13,200.00 | |
| 4 | X2810210 | STONE RIPRAP CL A5 SP | 119 | TON | $120.00 | $75.00 | |
| 5 | X5810103 | MEMB WTRPRF SYS B STR | 173 | SQ YD | $32.00 | $34.67 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,000.00 | $7,000.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,000.00 | $1,000.00 | |
| 8 | 25100630 | EROSION CONTR BLANKET | 1,341 | SQ YD | $2.00 | $3.85 | |
| 9 | 28000250 | TEMP EROS CONTR SEED | 30 | POUND | $3.00 | $60.50 | |
| 10 | 28000400 | PERIMETER EROS BAR | 731 | FOOT | $3.00 | $5.00 | |
| 11 | 28001100 | TEMP EROS CONTR BLANK | 1,341 | SQ YD | $2.00 | $0.5500 | |
| 12 | 30300112 | AGG SUBGRADE IMPR 12 | 532 | SQ YD | $26.00 | $25.00 | |
| 13 | 40600275 | BIT MATLS PR CT | 1,196 | POUND | $1.25 | $0.0100 | |
| 14 | 40600290 | BIT MATLS TACK CT | 110 | POUND | $3.10 | $5.50 | |
| 15 | 40603080 | HMA BC IL-19.0 N50 | 69 | TON | $220.00 | $180.00 | |
| 16 | 40604050 | HMA SC IL-9.5 C N50 | 41 | TON | $340.00 | $180.00 | |
| 17 | 44000100 | PAVEMENT REM | 504 | SQ YD | $16.90 | $20.00 | |
| 18 | 50100100 | REM EXIST STRUCT | 1 | EACH | $25,000.00 | $30,000.00 | |
| 19 | 50105220 | PIPE CULVERT REMOV | 20 | FOOT | $40.00 | $50.00 | |
| 20 | 50800205 | REINF BARS, EPOXY CTD | 25,920 | POUND | $2.10 | $3.00 | |
| 21 | 51500100 | NAME PLATES | 1 | EACH | $950.00 | $1,000.00 | |
| 22 | 54003000 | CONC BOX CUL | 205.9 | CU YD | $940.00 | $950.00 | |
| 23 | 59100100 | GEOCOMPOSITE WALL DR | 173 | SQ YD | $38.00 | $40.83 | |
| 24 | 63200310 | GUARDRAIL REMOV | 118 | FOOT | $20.00 | $10.00 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $26,310.00 | $26,850.00 |