18-17119-02-BR
- Let date
- Friday, March 11, 2022
- Contract
- 87773 · job page
- District
- District 3
- County
- Livingston
- Highway
- Limits
- Replace the bridge carrying TR 70 over Mud Creek, 2.5 miles southeast of Manville.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Tobey's Construction & Cartage, Inc. Low bidder | $406,355 | ||
| 2 | H. J. Eppel & Co. | $416,832 | +2.6% | |
| 3 | Riber Construction, Inc. | $447,484 | +10.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Tobey's Constru… | #2 H. J. Eppel & C… | #3 Riber Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2070302 | POROUS GRAN EMB SPEC | 130 | TON | $30.00 | $46.00 | $45.00 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 0.3 | ACRE | $10,000.00 | $11,075.00 | $10,000.00 | |
| 3 | 20200100 | EARTH EXCAVATION | 360 | CU YD | $38.00 | $48.00 | $48.00 | |
| 4 | 20300100 | CHANNEL EXCAVATION | 115 | CU YD | $38.00 | $52.00 | $31.00 | |
| 5 | 20400800 | FURNISHED EXCAVATION | 55 | CU YD | $25.00 | $82.00 | $50.00 | |
| 6 | 28000305 | TEMP DITCH CHECKS | 8 | FOOT | $20.00 | $18.00 | $110.00 | |
| 7 | 28000400 | PERIMETER EROS BAR | 415 | FOOT | $1.80 | $6.25 | $1.80 | |
| 8 | 28100107 | STONE RIPRAP CL A4 | 320 | SQ YD | $75.00 | $85.00 | $81.00 | |
| 9 | 28200200 | FILTER FABRIC | 320 | SQ YD | $2.50 | $6.00 | $4.00 | |
| 10 | 35100100 | AGG BASE CSE A | 663 | TON | $40.00 | $44.00 | $41.00 | |
| 11 | 40600275 | BIT MATLS PR CT | 2,025 | POUND | $1.00 | $1.75 | $1.00 | |
| 12 | 40600290 | BIT MATLS TACK CT | 200 | POUND | $0.6000 | $1.75 | $0.6000 | |
| 13 | 40603080 | HMA BC IL-19.0 N50 | 125 | TON | $158.00 | $134.00 | $158.00 | |
| 14 | 40604050 | HMA SC IL-9.5 C N50 | 70 | TON | $163.00 | $134.00 | $163.00 | |
| 15 | 48101200 | AGGREGATE SHLDS B | 180 | TON | $42.00 | $46.00 | $60.00 | |
| 16 | 50100100 | REM EXIST STRUCT | 1 | EACH | $19,000.00 | $20,000.00 | $22,600.00 | |
| 17 | 50300225 | CONC STRUCT | 26.2 | CU YD | $1,000.00 | $900.00 | $1,250.00 | |
| 18 | 50400405 | P P CONC DK BM 21 DP | 1,484 | SQ FT | $92.00 | $96.50 | $95.00 | |
| 19 | 50800205 | REINF BARS, EPOXY CTD | 3,300 | POUND | $2.75 | $3.95 | $2.75 | |
| 20 | 50900205 | STEEL RAILING TY S1 | 112 | FOOT | $127.75 | $160.00 | $127.50 | |
| 21 | 51201400 | FUR STL PILE HP10X42 | 245 | FOOT | $87.00 | $76.00 | $55.00 | |
| 22 | 51202305 | DRIVING PILES | 245 | FOOT | $0.0100 | $0.1000 | $0.0100 | |
| 23 | 51203400 | TEST PILE ST HP10X42 | 1 | EACH | $10,500.00 | $8,500.00 | $30,000.00 | |
| 24 | 51204650 | PILE SHOES | 8 | EACH | $160.00 | $200.00 | $95.00 | |
| 25 | 51500100 | NAME PLATES | 1 | EACH | $500.00 | $450.00 | $500.00 | |
| 26 | 60100060 | CONC HDWL FOR P DRAIN | 4 | EACH | $400.00 | $590.00 | $500.00 | |
| 27 | 60146304 | P UNDR FOR STRUCT 4 | 118 | FOOT | $25.00 | $35.00 | $0.0100 | |
| 28 | 63100075 | TRAF BAR TERM T5A | 4 | EACH | $1,925.00 | $1,684.00 | $1,925.00 | |
| 29 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,450.00 | $3,775.00 | $3,450.00 | |
| 30 | 67100100 | MOBILIZATION | 1 | L SUM | $22,000.00 | $5,000.00 | $26,820.00 | |
| 31 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $45.00 | $41.00 | $45.00 |