18-09110-02-BR
- Let date
- Friday, January 15, 2021
- Contract
- 87755 · job page
- District
- District 3
- County
- Livingston
- Highway
- Limits
- Replace the bridge carrying TR 118 over Mud Creek, 3.5 miles northeast of Cornell.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Riber Construction, Inc. Low bidder | $380,342 | ||
| 2 | Gensini Excavating, Inc. | $382,219 | +0.5% | |
| 3 | Tobey's Construction & Cartage, Inc. | $404,896 | +6.5% | |
| 4 | H. J. Eppel & Co. | $452,245 | +18.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Riber Construct… | #2 Gensini Excavat… | #3 Tobey's Constru… | #4 H. J. Eppel & C… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2070302 | POROUS GRAN EMB SPEC | 110 | TON | $24.00 | $30.00 | $32.00 | $39.00 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 0.3 | ACRE | $9,650.00 | $15,000.00 | $9,650.00 | $10,306.80 | |
| 3 | Z0046304 | P UNDR FOR STRUCT 4 | 108 | FOOT | $10.00 | $30.00 | $8.00 | $18.50 | |
| 4 | 20100500 | TREE REMOV ACRES | 0.1 | ACRE | $8,800.00 | $10,000.00 | $8,750.00 | $67,860.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 138 | CU YD | $31.00 | $15.00 | $35.00 | $53.30 | |
| 6 | 20300100 | CHANNEL EXCAVATION | 190 | CU YD | $19.00 | $15.00 | $35.00 | $45.00 | |
| 7 | 20400800 | FURNISHED EXCAVATION | 170 | CU YD | $47.00 | $20.00 | $15.00 | $49.50 | |
| 8 | 28100107 | STONE RIPRAP CL A4 | 403 | SQ YD | $66.00 | $60.00 | $70.00 | $80.00 | |
| 9 | 28200200 | FILTER FABRIC | 403 | SQ YD | $4.00 | $2.00 | $1.50 | $6.00 | |
| 10 | 35100100 | AGG BASE CSE A | 645 | TON | $33.00 | $25.00 | $40.00 | $43.00 | |
| 11 | 40600275 | BIT MATLS PR CT | 1,785 | POUND | $0.0100 | $1.00 | $0.0100 | $1.30 | |
| 12 | 40600290 | BIT MATLS TACK CT | 176 | POUND | $0.0100 | $1.00 | $1.16 | $1.60 | |
| 13 | 40603080 | HMA BC IL-19.0 N50 | 110 | TON | $120.00 | $150.00 | $166.00 | $119.00 | |
| 14 | 40604050 | HMA SC IL-9.5 C N50 | 66 | TON | $140.00 | $185.00 | $166.00 | $120.00 | |
| 15 | 48101200 | AGGREGATE SHLDS B | 75 | TON | $17.00 | $35.00 | $45.00 | $52.00 | |
| 16 | 50100100 | REM EXIST STRUCT | 1 | EACH | $22,000.00 | $12,500.00 | $12,500.00 | $19,680.00 | |
| 17 | 50300225 | CONC STRUCT | 25.8 | CU YD | $1,025.00 | $1,100.00 | $1,150.00 | $1,180.00 | |
| 18 | 50400505 | P P CONC DK BM 27 DP | 1,701 | SQ FT | $76.20 | $87.00 | $80.00 | $87.50 | |
| 19 | 50800205 | REINF BARS, EPOXY CTD | 3,260 | POUND | $2.30 | $2.00 | $2.00 | $2.85 | |
| 20 | 50900205 | STEEL RAILING TY S1 | 124 | FOOT | $139.70 | $120.00 | $165.00 | $146.50 | |
| 21 | 51200957 | FUR M S PILE 12X0.250 | 540 | FOOT | $57.00 | $80.00 | $72.00 | $103.00 | |
| 22 | 51202305 | DRIVING PILES | 540 | FOOT | $0.1000 | $0.0100 | $0.0100 | $0.2500 | |
| 23 | 51203200 | TEST PILE MET SHELLS | 1 | EACH | $15,000.00 | $10,000.00 | $8,750.00 | $12,850.00 | |
| 24 | 51500100 | NAME PLATES | 1 | EACH | $450.00 | $500.00 | $400.00 | $430.00 | |
| 25 | 542C1081 | P CUL CL C 2 36 | 46 | FOOT | $63.00 | $100.00 | $105.00 | $91.00 | |
| 26 | 66500105 | WOV W FENCE 4 | 559 | FOOT | $17.00 | $20.00 | $38.55 | $27.30 | |
| 27 | 67100100 | MOBILIZATION | 1 | L SUM | $22,012.00 | $7,500.00 | $15,500.00 | $6,785.00 | |
| 28 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $40.00 | $50.00 | $35.00 | $42.00 |