18-28129-00-BR
- Let date
- Friday, April 24, 2020
- Contract
- 87729 · job page
- District
- District 3
- County
- Livingston
- Highway
- Limits
- Replace the bridge carrying TR 41D over Mud Creek, 2.5 miles southeast of Blackstone.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Riber Construction, Inc. Low bidder | $310,925 | ||
| 2 | H. J. Eppel & Co. | $322,305 | +3.7% | |
| 3 | Tobey's Construction & Cartage, Inc. | $323,543 | +4.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Riber Construct… | #2 H. J. Eppel & C… | #3 Tobey's Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.25 | ACRE | $11,320.00 | $11,886.00 | $11,320.00 | |
| 2 | Z0046304 | P UNDR FOR STRUCT 4 | 123 | FOOT | $24.00 | $20.00 | $13.00 | |
| 3 | 20200100 | EARTH EXCAVATION | 85 | CU YD | $70.00 | $80.00 | $35.00 | |
| 4 | 20300100 | CHANNEL EXCAVATION | 549 | CU YD | $26.00 | $41.00 | $35.00 | |
| 5 | 20700110 | POROUS GRAN EMBANK | 109 | TON | $44.00 | $36.00 | $38.00 | |
| 6 | 28000250 | TEMP EROS CONTR SEED | 20 | POUND | $1.00 | $7.00 | $6.00 | |
| 7 | 28000305 | TEMP DITCH CHECKS | 40 | FOOT | $25.00 | $14.00 | $15.00 | |
| 8 | 28000400 | PERIMETER EROS BAR | 540 | FOOT | $6.00 | $6.50 | $3.00 | |
| 9 | 28100207 | STONE RIPRAP CL A4 | 170 | TON | $134.00 | $72.50 | $118.00 | |
| 10 | 28200200 | FILTER FABRIC | 282 | SQ YD | $4.00 | $4.75 | $1.50 | |
| 11 | 40200800 | AGG SURF CSE B | 205 | TON | $27.00 | $41.00 | $43.00 | |
| 12 | 50100100 | REM EXIST STRUCT | 1 | EACH | $17,760.00 | $17,500.00 | $21,000.00 | |
| 13 | 50300225 | CONC STRUCT | 27.4 | CU YD | $1,020.00 | $1,190.00 | $1,150.00 | |
| 14 | 50400505 | P P CONC DK BM 27 DP | 1,818 | SQ FT | $71.00 | $75.00 | $71.00 | |
| 15 | 50800205 | REINF BARS, EPOXY CTD | 4,310 | POUND | $1.80 | $2.45 | $2.00 | |
| 16 | 50900205 | STEEL RAILING TY S1 | 135 | FOOT | $109.05 | $119.95 | $109.05 | |
| 17 | 51200957 | FUR M S PILE 12X0.250 | 424 | FOOT | $48.00 | $77.00 | $70.00 | |
| 18 | 51202305 | DRIVING PILES | 424 | FOOT | $0.1000 | $0.1000 | $1.00 | |
| 19 | 51203200 | TEST PILE MET SHELLS | 1 | EACH | $16,000.00 | $8,000.00 | $8,000.00 | |
| 20 | 51500100 | NAME PLATES | 1 | EACH | $400.00 | $430.00 | $450.00 | |
| 21 | 67100100 | MOBILIZATION | 1 | L SUM | $12,200.00 | $2,200.00 | $17,500.00 | |
| 22 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $40.00 | $208.00 | $40.00 |