23-00185-17-PP
- Let date
- Friday, June 12, 2026
- Contract
- 85792 · job page
- District
- District 2
- County
- Stephenson
- Highway
- Limits
- Cold-in-place recycling on Orangeville Road from McConnell Road to IL 26.
- Classification
- ·
- Project number
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | W K Construction Company, Inc. Low bidder | $582,004 | ||
| 2 | Dunn Company | $769,411 | +32.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 W K Constructio… | #2 Dunn Company |
|---|---|---|---|---|---|---|---|
| 1 | LR400015 | ADD ROCK | 73,963 | SQ YD | $0.0100 | $0.0100 | |
| 2 | LR400055 | CIR-FDR EMULS ASPHALT | 462 | TON | $150.00 | $200.00 | |
| 3 | LR400750 | CIP RECYCLING 5.0 | 73,963 | SQ YD | $5.39 | $7.25 | |
| 4 | LR403300 | SURFACE PROFILE MILL | 73,963 | SQ YD | $0.5000 | $0.7500 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $34,000.00 | $26,257.00 | |
| 6 | 67100100 | MOBILIZATION | 1 | L SUM | $34,000.00 | $52,208.00 | |
| 7 | 70300100 | SHORT TERM PAVT MKING | 2,774 | FOOT | $3.00 | $2.20 |