13-00040-01-BT
- Let date
- Friday, June 11, 2021
- Contract
- 85708 · job page
- District
- District 2
- County
- Winnebago
- Highway
- Limits
- On-Street bike routes on various roadways in South Beloit. Project includes signing, pavement markings, sidewalk replacement, curb and gutter replacement, HMA surfce course, and pdestrian signals.
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Norwest Construction, Inc. Low bidder | $379,485 | ||
| 2 | Alliance Contractors, Inc. | $386,071 | +1.7% | |
| 3 | N-Trak Group LLC | $438,416 | +15.5% | |
| 4 | Stenstrom Excavation & Blacktop, Inc. | $496,687 | +30.9% | |
| 5 | Electric Conduit Construction | $544,002 | +43.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Norwest Constru… | #2 Alliance Contra… | #3 N-Trak Group LLC | #4 Stenstrom Excav… | #5 Electric Condui… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | XX000970 | PARKWAY RESTORATION | 1 | L SUM | $9,200.00 | $20,000.00 | $30,000.00 | $5,000.00 | $24,560.40 | |
| 2 | XX008872 | SLR-PWR PED CSS COMP | 2 | EACH | $1,700.00 | $7,607.00 | $9,400.00 | $9,200.00 | $16,638.60 | |
| 3 | X0325936 | SOLPWR FLR/PM YEL LED | 2 | EACH | $2,700.00 | $4,913.00 | $2,900.00 | $2,840.00 | $3,063.50 | |
| 4 | X0326806 | WASHOUT BASIN | 1 | L SUM | $500.00 | $1.00 | $700.00 | $685.00 | $1,000.00 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $17,000.00 | $12,000.00 | $17,000.00 | $26,620.00 | $12,600.00 | |
| 6 | Z0012450 | CONCRETE STEPS | 5 | CU YD | $1,700.00 | $1,423.75 | $1,750.00 | $1,500.00 | $1,260.00 | |
| 7 | 28000510 | INLET FILTERS | 21 | EACH | $100.00 | $50.00 | $75.00 | $0.0100 | $162.75 | |
| 8 | 35101600 | AGG BASE CSE B 4 | 954 | SQ YD | $13.00 | $4.00 | $7.25 | $17.20 | $13.65 | |
| 9 | 35101800 | AGG BASE CSE B 6 | 30 | SQ YD | $23.00 | $6.00 | $56.00 | $19.80 | $14.70 | |
| 10 | 35102000 | AGG BASE CSE B 8 | 157 | SQ YD | $29.00 | $8.00 | $8.50 | $22.40 | $15.75 | |
| 11 | 35102400 | AGG BASE CSE B 12 | 381 | SQ YD | $41.00 | $12.00 | $15.00 | $25.70 | $16.80 | |
| 12 | 35300100 | PCC BSE CSE 6 | 188 | SQ YD | $80.00 | $69.50 | $50.00 | $63.00 | $70.88 | |
| 13 | 40600275 | BIT MATLS PR CT | 354 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $3.72 | |
| 14 | 40600290 | BIT MATLS TACK CT | 81 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.8500 | |
| 15 | 40604060 | HMA SC IL-9.5 D N50 | 60 | TON | $306.00 | $305.75 | $320.00 | $385.00 | $321.04 | |
| 16 | 42000100 | PCC PVT 6 | 17 | SQ YD | $95.00 | $70.20 | $135.00 | $109.00 | $73.50 | |
| 17 | 42000400 | PCC PVT 9 | 53 | SQ YD | $105.00 | $82.50 | $75.00 | $119.00 | $136.50 | |
| 18 | 42400200 | PC CONC SIDEWALK 5 | 8,579 | SQ FT | $6.70 | $8.10 | $8.50 | $10.50 | $10.50 | |
| 19 | 42400800 | DETECTABLE WARNINGS | 761 | SQ FT | $23.50 | $25.00 | $30.00 | $30.00 | $33.00 | |
| 20 | 44000100 | PAVEMENT REM | 241 | SQ YD | $29.00 | $40.00 | $10.00 | $10.70 | $23.10 | |
| 21 | 44000200 | DRIVE PAVEMENT REM | 187 | SQ YD | $29.00 | $20.00 | $10.00 | $11.80 | $12.60 | |
| 22 | 44000500 | COMB CURB GUTTER REM | 1,095 | FOOT | $11.00 | $25.00 | $15.00 | $10.20 | $10.50 | |
| 23 | 44000600 | SIDEWALK REM | 7,999 | SQ FT | $2.00 | $3.30 | $5.00 | $1.45 | $10.50 | |
| 24 | 44000690 | HMA SURF CORRECTION | 341 | SQ YD | $27.00 | $21.83 | $23.00 | $37.00 | $22.92 | |
| 25 | 50900805 | PEDESTRIAN RAIL | 20 | FOOT | $200.00 | $250.00 | $230.00 | $108.00 | $171.15 | |
| 26 | 60250200 | CB ADJUST | 1 | EACH | $1,200.00 | $475.00 | $1,000.00 | $700.00 | $500.00 | |
| 27 | 60255500 | MAN ADJUST | 3 | EACH | $1,200.00 | $475.00 | $800.00 | $700.00 | $650.00 | |
| 28 | 60260100 | INLETS ADJUST | 12 | EACH | $1,350.00 | $475.00 | $900.00 | $700.00 | $1,100.00 | |
| 29 | 60604700 | COMB CC&G TB6.18 MOD | 101 | FOOT | $40.00 | $39.00 | $47.00 | $117.00 | $41.00 | |
| 30 | 60610100 | COMB CC&G TM6.18 MOD | 903 | FOOT | $41.00 | $39.00 | $33.00 | $117.00 | $42.00 | |
| 31 | 60610700 | COMB CC&G TM6.24 MOD | 91 | FOOT | $46.00 | $40.75 | $48.00 | $121.00 | $53.00 | |
| 32 | 67100100 | MOBILIZATION | 1 | L SUM | $12,500.00 | $15,890.68 | $30,000.00 | $9,248.59 | $34,638.84 | |
| 33 | 72000100 | SIGN PANEL T1 | 201 | SQ FT | $34.00 | $20.00 | $34.00 | $34.70 | $37.80 | |
| 34 | 72400710 | RELOC SIGN PANEL T1 | 2 | SQ FT | $306.00 | $50.00 | $300.00 | $53.90 | $105.00 | |
| 35 | 72800100 | TELES STL SIN SUPPORT | 26 | FOOT | $26.00 | $15.00 | $26.00 | $20.50 | $23.10 | |
| 36 | 72900100 | METAL POST TY A | 367 | FOOT | $21.00 | $9.50 | $20.00 | $20.25 | $21.00 | |
| 37 | 78000100 | THPL PVT MK LTR & SYM | 540 | SQ FT | $5.60 | $5.50 | $5.75 | $10.80 | $16.80 | |
| 38 | 78000400 | THPL PVT MK LINE 6 | 1,912 | FOOT | $2.60 | $2.55 | $2.60 | $2.70 | $1.58 | |
| 39 | 78005100 | EPOXY PVT MK LTR-SYM | 300 | SQ FT | $12.02 | $12.00 | $12.50 | $15.10 | $21.00 | |
| 40 | 78005130 | EPOXY PVT MK LINE 6 | 694 | FOOT | $6.00 | $5.85 | $6.00 | $3.80 | $2.10 | |
| 41 | 78300201 | PAVMT MRKG REM GRIND | 80 | SQ FT | $2.00 | $2.50 | $2.60 | $10.80 | $10.50 | |
| 42 | 81028750 | UNDRGRD C CNC 2 | 189 | FOOT | $39.00 | $34.10 | $42.00 | $41.25 | $48.28 | |
| 43 | 87301215 | ELCBL C SIGNAL 14 2C | 207 | FOOT | $2.20 | $1.30 | $2.30 | $2.30 | $21.84 | |
| 44 | 87601100 | PED P-B POST GALVS T1 | 6 | EACH | $2,030.00 | $1,529.00 | $2,200.00 | $2,145.00 | $2,409.00 |