12-00142-00-BR
- Let date
- Friday, March 9, 2018
- Contract
- 85663 · job page
- District
- District 2
- County
- Jo Daviess
- Highway
- Limits
- Replace the existing bridge with a 3-cell box culvert to carry Stagecoach Trail over the West Branch of Clear Creek, 3 miles west of Warren.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | M & M Concrete, Inc. Low bidder | $409,500 | ||
| 2 | Civil Constructors, Inc. | $450,463 | +10.0% | |
| 3 | Martin & Company Excavating | $521,509 | +27.4% | |
| 4 | Sjostrom & Sons, Inc. | $559,449 | +36.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 M & M Concrete,… | #2 Civil Construct… | #3 Martin & Compan… | #4 Sjostrom & Sons… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2010400 | STUMP REMOVAL ONLY | 82 | UNIT | $20.00 | $40.00 | $45.00 | $32.54 | |
| 2 | X2020410 | EARTH EXCAVATION SPL | 1,944 | CU YD | $20.00 | $16.00 | $19.35 | $31.58 | |
| 3 | X2070302 | POROUS GRAN EMB SPEC | 303 | TON | $40.00 | $26.00 | $29.00 | $26.83 | |
| 4 | X2501020 | SEEDING CL 2A SPL | 1.1 | ACRE | $3,500.00 | $2,000.00 | $3,000.00 | $5,385.21 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $2,800.00 | $2,800.00 | $3,000.00 | $5,417.75 | |
| 6 | Z0022810 | FENCE REMOVAL SPECIAL | 600 | FOOT | $5.00 | $2.00 | $3.00 | $4.30 | |
| 7 | 20200200 | ROCK EXCAVATION | 25 | CU YD | $81.00 | $175.00 | $200.00 | $115.65 | |
| 8 | 20201200 | REM & DISP UNS MATL | 25 | CU YD | $40.00 | $18.00 | $18.00 | $68.56 | |
| 9 | 20300100 | CHANNEL EXCAVATION | 200 | CU YD | $23.00 | $26.00 | $36.00 | $40.79 | |
| 10 | 25100630 | EROSION CONTR BLANKET | 5,322 | SQ YD | $1.25 | $2.00 | $2.35 | $1.95 | |
| 11 | 28000250 | TEMP EROS CONTR SEED | 110 | POUND | $3.00 | $2.00 | $11.00 | $4.34 | |
| 12 | 28000305 | TEMP DITCH CHECKS | 890 | FOOT | $4.00 | $10.00 | $12.00 | $10.85 | |
| 13 | 28000400 | PERIMETER EROS BAR | 2,240 | FOOT | $2.75 | $2.00 | $2.50 | $3.69 | |
| 14 | 28000500 | INLET & PIPE PROTECT | 2 | EACH | $300.00 | $125.00 | $140.00 | $245.47 | |
| 15 | 28100105 | STONE RIPRAP CL A3 | 15 | SQ YD | $44.00 | $40.00 | $44.00 | $60.31 | |
| 16 | 28100109 | STONE RIPRAP CL A5 | 110 | SQ YD | $46.00 | $48.00 | $52.00 | $95.75 | |
| 17 | 28200200 | FILTER FABRIC | 110 | SQ YD | $3.00 | $2.50 | $3.00 | $4.71 | |
| 18 | 35100100 | AGG BASE CSE A | 1,440 | TON | $17.00 | $17.00 | $19.30 | $28.03 | |
| 19 | 40200800 | AGG SURF CSE B | 174 | TON | $18.00 | $15.00 | $17.50 | $28.03 | |
| 20 | 40600275 | BIT MATLS PR CT | 5,567 | POUND | $0.8000 | $0.8000 | $1.00 | $0.8700 | |
| 21 | 40600290 | BIT MATLS TACK CT | 557 | POUND | $1.45 | $1.45 | $2.00 | $1.57 | |
| 22 | 40603080 | HMA BC IL-19.0 N50 | 416 | TON | $73.00 | $73.00 | $88.00 | $79.18 | |
| 23 | 40603310 | HMA SC "C" N50 | 277 | TON | $76.00 | $76.00 | $88.00 | $82.43 | |
| 24 | 48101200 | AGGREGATE SHLDS B | 231 | TON | $20.00 | $18.00 | $26.00 | $25.30 | |
| 25 | 50100100 | REM EXIST STRUCT | 1 | EACH | $14,565.00 | $18,226.00 | $8,500.00 | $22,431.53 | |
| 26 | 50200100 | STRUCTURE EXCAVATION | 350 | CU YD | $21.00 | $22.00 | $40.00 | $33.97 | |
| 27 | 50800205 | REINF BARS, EPOXY CTD | 41,540 | POUND | $1.40 | $1.42 | $2.44 | $1.60 | |
| 28 | 51500100 | NAME PLATES | 1 | EACH | $550.00 | $471.00 | $575.00 | $641.27 | |
| 29 | 54003000 | CONC BOX CUL | 219.9 | CU YD | $515.00 | $699.00 | $688.00 | $737.68 | |
| 30 | 542C0223 | P CUL CL C 1 18 | 102 | FOOT | $33.00 | $40.00 | $44.00 | $43.86 | |
| 31 | 54262718 | METAL FL END SEC 18" | 4 | EACH | $479.00 | $180.00 | $220.00 | $351.87 | |
| 32 | 63200310 | GUARDRAIL REMOV | 268 | FOOT | $8.00 | $3.00 | $4.00 | $5.61 | |
| 33 | 67100100 | MOBILIZATION | 1 | L SUM | $24,351.24 | $27,027.00 | $25,000.00 | $33,564.63 | |
| 34 | 78001110 | PAINT PVT MK LINE 4 | 2,230 | FOOT | $0.7500 | $0.7500 | $0.9000 | $0.9800 |