15-00151-00-BR
- Let date
- Friday, April 27, 2018
- Contract
- 85653 · job page
- District
- District 2
- County
- Jo Daviess
- Highway
- Limits
- Bridge rehabilitation with approach roadwork on CH 1 (West Council Hill Road) over the Galena River, 3 miles north of Galena.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Civil Constructors, Inc. Low bidder | $775,220 | ||
| 2 | Sjostrom & Sons, Inc. | $1,172,333 | +51.2% | |
| 3 | Kovilic Construction Company, Inc. | $1,411,291 | +82.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Civil Construct… | #2 Sjostrom & Sons… | #3 Kovilic Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2010400 | STUMP REMOVAL ONLY | 182 | UNIT | $10.30 | $50.00 | $60.00 | |
| 2 | X2020410 | EARTH EXCAVATION SPL | 159 | CU YD | $20.00 | $46.00 | $100.00 | |
| 3 | X2501020 | SEEDING CL 2A SPL | 0.29 | ACRE | $5,000.00 | $5,000.00 | $5,000.00 | |
| 4 | X5860110 | GRANULAR BACKFILL STR | 48 | CU YD | $75.00 | $65.00 | $100.00 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $2,400.00 | $2,400.00 | $20,000.00 | |
| 6 | Z0001900 | ASB BEARING PAD REMOV | 40 | EACH | $55.10 | $88.98 | $100.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $4,140.00 | $5,500.00 | $10,000.00 | |
| 8 | Z0022800 | FENCE REMOVAL | 382 | FOOT | $3.23 | $8.00 | $10.00 | |
| 9 | Z0023201 | SED CONT SILT CURTAIN | 2 | EACH | $1.00 | $10,000.00 | $10,000.00 | |
| 10 | 20201200 | REM & DISP UNS MATL | 10 | CU YD | $28.00 | $17.00 | $100.00 | |
| 11 | 20300100 | CHANNEL EXCAVATION | 593 | CU YD | $18.00 | $21.00 | $100.00 | |
| 12 | 20400800 | FURNISHED EXCAVATION | 70 | CU YD | $20.00 | $23.00 | $100.00 | |
| 13 | 25100630 | EROSION CONTR BLANKET | 1,384 | SQ YD | $3.00 | $3.00 | $3.00 | |
| 14 | 28000250 | TEMP EROS CONTR SEED | 29 | POUND | $5.00 | $95.00 | $50.00 | |
| 15 | 28000305 | TEMP DITCH CHECKS | 20 | FOOT | $20.00 | $20.00 | $50.00 | |
| 16 | 28000400 | PERIMETER EROS BAR | 669 | FOOT | $3.00 | $3.00 | $5.00 | |
| 17 | 28100109 | STONE RIPRAP CL A5 | 1,426 | SQ YD | $57.00 | $60.00 | $125.00 | |
| 18 | 28200200 | FILTER FABRIC | 1,426 | SQ YD | $1.00 | $2.25 | $5.00 | |
| 19 | 30300011 | AGG SUBGRADE IMPROVE | 255 | TON | $27.00 | $24.00 | $50.00 | |
| 20 | 40200800 | AGG SURF CSE B | 37 | TON | $25.00 | $18.00 | $50.00 | |
| 21 | 40600275 | BIT MATLS PR CT | 841 | POUND | $1.60 | $1.60 | $3.00 | |
| 22 | 40600290 | BIT MATLS TACK CT | 77 | POUND | $4.00 | $4.00 | $3.00 | |
| 23 | 40603080 | HMA BC IL-19.0 N50 | 44 | TON | $98.00 | $98.00 | $150.00 | |
| 24 | 40603310 | HMA SC "C" N50 | 101 | TON | $98.00 | $98.00 | $150.00 | |
| 25 | 48101200 | AGGREGATE SHLDS B | 53 | TON | $35.00 | $35.00 | $50.00 | |
| 26 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $65,000.00 | $107,862.91 | $175,000.00 | |
| 27 | 50102400 | CONC REM | 60.6 | CU YD | $247.00 | $1,511.17 | $500.00 | |
| 28 | 50200100 | STRUCTURE EXCAVATION | 72 | CU YD | $70.50 | $88.32 | $100.00 | |
| 29 | 50300225 | CONC STRUCT | 85.9 | CU YD | $644.00 | $2,215.66 | $1,500.00 | |
| 30 | 50300280 | CONCRETE ENCASEMENT | 2 | CU YD | $1,880.00 | $2,509.04 | $1,500.00 | |
| 31 | 50400405 | P P CONC DK BM 21 DP | 2,688 | SQ FT | $65.60 | $68.03 | $90.00 | |
| 32 | 50400605 | P P CONC DK BM 33 DP | 1,992 | SQ FT | $83.20 | $101.60 | $105.00 | |
| 33 | 50800205 | REINF BARS, EPOXY CTD | 7,000 | POUND | $2.00 | $4.39 | $3.00 | |
| 34 | 50901050 | STEEL RAILING TY SM | 394 | FOOT | $130.00 | $143.00 | $185.00 | |
| 35 | 51500100 | NAME PLATES | 1 | EACH | $405.00 | $529.45 | $750.00 | |
| 36 | 58100200 | WATERPRF MEMBRANE SYS | 526 | SQ YD | $32.05 | $30.00 | $90.00 | |
| 37 | 58300100 | PC MORTAR FAIRING CSE | 975 | FOOT | $1.80 | $3.80 | $10.00 | |
| 38 | 63100087 | TRAF BAR TERM T6A | 2 | EACH | $2,900.00 | $3,755.00 | $5,000.00 | |
| 39 | 63100169 | TR BAR TRM T1 SPL FLR | 2 | EACH | $2,350.00 | $2,875.00 | $4,000.00 | |
| 40 | 66700205 | PERM SURV MKRS T1 | 1 | EACH | $200.00 | $2,700.00 | $500.00 | |
| 41 | 67100100 | MOBILIZATION | 1 | L SUM | $46,512.00 | $70,340.87 | $50,000.00 | |
| 42 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $30.00 | $40.00 | $50.00 | |
| 43 | 78200005 | GRDRAIL REF TYPE A | 8 | EACH | $10.00 | $9.00 | $20.00 |