Bid tab 80B73

Let Nov 7, 2025 · District 1 · Cook

‹ Nov 2025 results

2025-2043-GRF

Let date
Friday, November 7, 2025
Contract
80B73 · job page
District
District 1
County
Cook
Highway
Limits
The project consists of GRAFFITI REMOVAL and shall consist of removing graffiti from the surfaces on State DOT right of way located on the inbound and outbound mainlines and ramps of the Kennedy (I-90/94), Dan Ryan (I-90/94), Bishop Ford (I-94), the Stevenson (I-55), and I-57 Expressways in Cook County.
Classification
GRAFFITI REMOVAL and shall consist of removing graffiti from the surfaces on State DOT right of way located on ·
Project number

Bidders 1

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 ERA-Valdivia Contractors, Inc. Low bidder $1,110,000

Bid tab: unit prices 2 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 ERA-Valdivia Co…
1X0300062 GRAFFITI REMOVAL20,000SQ YD $53.00
267100100 MOBILIZATION1L SUM $50,000.00