Bid tab 80B66

Let Jun 12, 2026 · District 1 · Cook

‹ Jun 2026 results

(3233-211-VB) I 25

Let date
Friday, June 12, 2026
Contract
80B66 · job page
District
District 1
County
Cook
Highway
Limits
This is a permanent protective shielding project and the work to be performed under this contract consists of installation of permanent protective shielding as shown on the plans and any incidental and collateral work necessary to complete located at various structures carrying Circle Ave, Harlem Ave and California Ave Over I-290 (Eisenhower) in the Villages of Oak Park, Forest Park and City of Chicago, in Cook County.
Classification
Installation of permanent protective shielding as shown on the plans and any incidental and collateral work ne ·
Project number

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Lorig Construction Company Low bidder $397,833
2 Areatha Construction Co., Inc. $457,975 +15.1%
3 Acura Inc. $498,576 +25.3%
4 Martam Construction Incorporated $588,491 +47.9%

Bid tab: unit prices 7 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Lorig Construct…#2 Areatha Constru…#3 Acura Inc.#4 Martam Construc…
1X5017305 PROTEC SHIELD PERM2,737SQ YD $100.00 $121.55 $70.00 $127.00
2X5017311 REM EX PROTEC SHIELD109SQ YD $80.00 $99.05 $40.00 $112.00
3X6700407 ENGRS FLD OFC TY A D112CAL MO $2,500.00 $3,000.00 $4,000.00 $4,800.00
4X7011015 TR C-PROT EXPRESSWAYS1L SUM $63,000.00 $45,000.00 $200,000.00 $126,000.00
5X7200061 TEMP INFO SIGNING154.2SQ FT $15.00 $15.00 $30.00 $20.00
667100100 MOBILIZATION1L SUM $20,000.00 $27,440.00 $30,000.00 $34,000.00
770200100 NIGHT WORK ZONE LIGHT1L SUM $100.00 $3,742.75 $20,000.00 $8,000.00