111RS-4
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $1,618,916 | ||
| 2 | E. T. Simonds Construction Company | $1,771,542 | +9.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|
| 1 | X4430201 | AREA REF CR CTRL TRMT | 39,922 | SQ YD | $2.85 | $3.10 | |
| 2 | 40600290 | BIT MATLS TACK CT | 26,648 | POUND | $0.0100 | $0.0100 | |
| 3 | 40600370 | LONG JOINT SEALANT | 14,905 | FOOT | $2.50 | $2.89 | |
| 4 | 40600400 | MIX CR JTS FLANGEWYS | 10 | TON | $250.00 | $1,131.72 | |
| 5 | 40600405 | MATL TRANSFER DEVICE | 6,535 | TON | $1.30 | $3.05 | |
| 6 | 40600990 | TEMPORARY RAMP | 56 | SQ YD | $25.00 | $66.57 | |
| 7 | 40602970 | HMA BC IL-9.5FG N70 | 3,276 | TON | $90.00 | $98.82 | |
| 8 | 40604052 | HMA SC IL-9.5 C N70 | 3,411 | TON | $92.00 | $96.36 | |
| 9 | 40800050 | INCIDENTAL HMA SURF | 8 | TON | $150.00 | $90.61 | |
| 10 | 44000156 | HMA SURF REM 1 3/4 | 39,922 | SQ YD | $1.60 | $1.56 | |
| 11 | 44201411 | CL C PATCH T1 15 | 37 | SQ YD | $230.00 | $225.00 | |
| 12 | 44201415 | CL C PATCH T2 15 | 1,920 | SQ YD | $215.00 | $221.00 | |
| 13 | 44201419 | CL C PATCH T3 15 | 199 | SQ YD | $210.00 | $218.00 | |
| 14 | 44201421 | CL C PATCH T4 15 | 623 | SQ YD | $205.00 | $216.00 | |
| 15 | 48102100 | AGG WEDGE SHLD TYPE B | 828 | TON | $36.00 | $45.32 | |
| 16 | 64200214 | SINUSOIDAL RUM STP 14 | 14,905 | FOOT | $0.4500 | $0.7500 | |
| 17 | 67000400 | ENGR FIELD OFFICE A | 1 | CAL MO | $2,260.00 | $2,120.00 | |
| 18 | 67100100 | MOBILIZATION | 1 | L SUM | $97,000.00 | $89,522.15 | |
| 19 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $22,500.00 | $36,900.29 | |
| 20 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $5,000.00 | $38,843.58 | |
| 21 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $50.00 | $39.38 | |
| 22 | 70300100 | SHORT TERM PAVT MKING | 5,028 | FOOT | $1.50 | $1.57 | |
| 23 | 70300150 | SHRT TRM PAVT MK REM | 1,676 | SQ FT | $0.0100 | $0.0100 | |
| 24 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 37,027 | FOOT | $0.0100 | $0.0100 | |
| 25 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 33 | FOOT | $0.0100 | $0.0100 | |
| 26 | 78001110 | PAINT PVT MK LINE 4 | 37,027 | FOOT | $0.1600 | $0.1700 | |
| 27 | 78001180 | PAINT PVT MK LINE 24 | 33 | FOOT | $3.02 | $3.18 | |
| 28 | 78100100 | RAISED REFL PAVT MKR | 193 | EACH | $40.50 | $42.47 | |
| 29 | 78300200 | RAISED REF PVT MK REM | 193 | EACH | $14.00 | $11.15 | |
| 30 | 78300201 | PVT MKG REM GRINDING | 12,409 | SQ FT | $0.0100 | $0.0100 |