D9 TREE TRIMMING 2025-1

Let date
Friday, June 13, 2025
Contract
78B21 · job page
District
District 9
County
Union, Pulaski
Highway
Limits
9.3 miles of tree removal on I-57 from the IL 146 interchange to the Perks Road overpass.
Classification
·
Project number

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Sierra Bravo Contractors, LLC Low bidder $880,649
2 Homer Tree Service, Inc. $1,443,636 +63.9%
3 Samron Midwest Contracting, Inc. $2,452,330 +178.5%
4 Guinzy Construction,Inc. $2,880,161 +227.1%

Bid tab: unit prices 5 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Sierra Bravo Co…#2 Homer Tree Serv…#3 Samron Midwest …#4 Guinzy Construc…
1X6640638 TEMP CONSTR FENCE2,746FOOT $11.24 $10.00 $5.00 $22.72
220100500 TREE REMOV ACRES56.12ACRE $13,037.56 $19,800.00 $30,000.00 $43,168.64
367100100 MOBILIZATION1L SUM $52,277.54 $78,000.00 $145,000.00 $172,119.80
470100420 TRAF CONT-PROT 7014118EACH $2,595.45 $14,000.00 $0.0100 $21,818.00
570100700 TRAF CONT-PROT 7014061L SUM $45,074.53 $115,000.00 $610,000.00 $48,484.45