(41-9)RA(PP-1)
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $164,538 | ||
| 2 | Kinney Contractors, Inc. | $168,792 | +2.6% | |
| 3 | E. T. Simonds Construction Company | $169,170 | +2.8% | |
| 4 | G. M. Sipes Construction, Inc. | $191,561 | +16.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 Kinney Contract… | #3 E. T. Simonds C… | #4 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,500.00 | $12,500.00 | $9,134.85 | $3,000.00 | |
| 2 | 44200050 | WELDED WIRE REINF | 777 | SQ YD | $8.00 | $18.00 | $11.13 | $7.50 | |
| 3 | 44200934 | CL B PATCH T2 8 | 66 | SQ YD | $150.00 | $150.00 | $145.00 | $225.00 | |
| 4 | 44200942 | CL B PATCH T3 8 | 33 | SQ YD | $145.00 | $145.00 | $140.00 | $225.00 | |
| 5 | 44200944 | CL B PATCH T4 8 | 744 | SQ YD | $142.00 | $137.00 | $137.50 | $175.00 | |
| 6 | 44201299 | DOWEL BARS 1 1/2 | 196 | EACH | $28.00 | $23.00 | $25.26 | $35.00 | |
| 7 | 44213200 | SAW CUTS | 2,085 | FOOT | $5.00 | $0.0100 | $4.96 | $3.75 | |
| 8 | 44213204 | TIE BARS 3/4 | 392 | EACH | $16.00 | $17.00 | $12.80 | $15.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $9,000.00 | $11,000.00 | $13,463.33 | $9,000.00 | |
| 10 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $118.00 | $125.00 | $40.13 | $25.00 |