101PP-1
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $131,011 | ||
| 2 | Samron Midwest Contracting, Inc. | $163,104 | +24.5% | |
| 3 | Kinney Contractors, Inc. | $175,616 | +34.0% | |
| 4 | G. M. Sipes Construction, Inc. | $190,860 | +45.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … | #3 Kinney Contract… | #4 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 42000060 | WELDED WIRE REINF | 194 | SQ YD | $14.42 | $20.00 | $18.00 | $7.50 | |
| 2 | 44200929 | CL B PATCH T1 8 | 18 | SQ YD | $150.00 | $165.00 | $210.00 | $295.00 | |
| 3 | 44200934 | CL B PATCH T2 8 | 334 | SQ YD | $144.00 | $152.00 | $195.00 | $245.00 | |
| 4 | 44200942 | CL B PATCH T3 8 | 60 | SQ YD | $140.00 | $150.00 | $193.00 | $245.00 | |
| 5 | 44200944 | CL B PATCH T4 8 | 134 | SQ YD | $137.00 | $150.00 | $191.00 | $245.00 | |
| 6 | 44201299 | DOWEL BARS 1 1/2 | 962 | EACH | $17.60 | $32.00 | $25.00 | $20.00 | |
| 7 | 44213200 | SAW CUTS | 2,705 | FOOT | $3.84 | $5.75 | $4.00 | $4.00 | |
| 8 | 44213204 | TIE BARS 3/4 | 65 | EACH | $47.06 | $20.00 | $18.00 | $15.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $8,694.43 | $9,500.00 | $11,500.00 | $9,000.00 | |
| 10 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $10,484.65 | $16,000.00 | $15,000.00 | $14,000.00 | |
| 11 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $39.38 | $116.00 | $125.00 | $25.00 |