Bid tab 78970

Let Sep 22, 2023 · District 9 · Union Sign up free

‹ Sep 2023 results

104RS-7

Let date
Friday, September 22, 2023
Contract
78970 · job page
District
District 9
County
Union
Highway
Limits
2.6 miles of HMA surface removal and resurfacing on IL 146 / IL 127 from the Jonesboro Square to the IL 146 and IL 127 intersection.

Bidders 2

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 E. T. Simonds Construction Company Low bidder $1,974,043
2 Samron Midwest Contracting, Inc. $2,048,165 +3.8%

Bid tab: unit prices 48 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 E. T. Simonds C…#2 Samron Midwest …
1X2503100 MOWING136UNIT $10.79 $15.00
2Z0034105 MATL TRANSFER DEVICE8,442TON $3.36 $1.75
340600290 BIT MATLS TACK CT32,282POUND $0.0100 $0.0100
440600370 LONG JOINT SEALANT15,952FOOT $3.13 $3.00
540600990 TEMPORARY RAMP1,323SQ YD $0.0100 $6.50
640603085 HMA BC IL-19.0 N705,036TON $81.24 $85.00
740604062 HMA SC IL-9.5 D N703,406TON $106.03 $95.00
840800050 INCIDENTAL HMA SURF133TON $191.68 $250.00
944000155 HMA SURF REM 1 1/226,819SQ YD $2.03 $2.60
1044000164 HMA SURF REM 3 3/420,432SQ YD $3.66 $4.40
1144200050 WELDED WIRE REINF464SQ YD $17.44 $10.00
1244201385 CL C PATCH T1 1314SQ YD $180.00 $220.00
1344201389 CL C PATCH T2 13500SQ YD $177.00 $220.00
1444201394 CL C PATCH T3 13248SQ YD $174.00 $215.00
1544201396 CL C PATCH T4 13217SQ YD $170.00 $210.00
1648102100 AGG WEDGE SHLD TYPE B429TON $43.79 $45.00
1748203100 HMA SHOULDERS1,531TON $92.99 $134.00
1863000001 SPBGR TY A 6FT POSTS237.5FOOT $39.90 $65.00
1963000003 SPBGR TY A 9FT POSTS3,000FOOT $44.75 $55.00
2063000019 NON-BLOCKED SPBGR 6FT P317.2FOOT $68.25 $59.00
2163000030 SPGR ATT TO CULVERT125FOOT $357.00 $422.00
2263000050 WPGR ATT CLVRT CASE 1100FOOT $236.25 $310.00
2363100045 TRAF BAR TERM T28EACH $1,942.50 $2,450.00
2463100085 TRAF BAR TERM T64EACH $6,258.00 $5,900.00
2563100167 TR BAR TRM T1 SPL TAN12EACH $4,725.00 $3,825.00
2663200310 GUARDRAIL REMOV4,059FOOT $6.83 $6.25
2764200108 SHOULDER RUM STRIP 815,402FOOT $0.4100 $0.4500
2867000400 ENGR FIELD OFFICE A10CAL MO $1,800.00 $1,400.00
2967100100 MOBILIZATION1L SUM $151,089.05 $100,000.00
3070100460 TRAF CONT-PROT 7013061L SUM $37,040.02 $5,000.00
3170100600 TRAF CONT-PROT 7013361L SUM $11,546.59 $7,000.00
3270102620 TR CONT & PROT 7015011L SUM $0.0100 $2,000.00
3370102635 TR CONT & PROT 7017011L SUM $0.0100 $1,000.00
3470103815 TR CONT SURVEILLANCE15CAL DA $0.0100 $0.0100
3570107025 CHANGEABLE MESSAGE SN28CAL DA $40.50 $125.00
3670300100 SHORT TERM PAVT MKING4,112FOOT $1.53 $1.50
3770300150 SHRT TRM PAVT MK REM1,448SQ FT $0.0100 $2.50
3870300221 TEMP PVT MK LINE 4 - PAINT33,087FOOT $0.0100 $0.0100
3970300261 TEMP PVT MK LINE 12 - PAINT104FOOT $0.0100 $0.0100
4070300281 TEMP PVT MK LINE 24 - PAINT96FOOT $0.0100 $0.0100
4172501000 TERMINAL MARKER - DA12EACH $52.50 $50.00
4278000200 THPL PVT MK LINE 433,087FOOT $0.8100 $0.9000
4378000600 THPL PVT MK LINE 12104FOOT $2.47 $2.75
4478000650 THPL PVT MK LINE 2496FOOT $5.25 $5.75
4578100100 RAISED REFL PAVT MKR206EACH $40.95 $44.00
4678200005 GRDRAIL REF TYPE A52EACH $10.50 $12.00
4778300200 RAISED REF PVT MK REM81EACH $12.19 $13.00
4878300201 PAVMT MRKG REM GRIND11,333SQ FT $0.0100 $0.0100