104RS-7
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $1,974,043 | ||
| 2 | Samron Midwest Contracting, Inc. | $2,048,165 | +3.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X2503100 | MOWING | 136 | UNIT | $10.79 | $15.00 | |
| 2 | Z0034105 | MATL TRANSFER DEVICE | 8,442 | TON | $3.36 | $1.75 | |
| 3 | 40600290 | BIT MATLS TACK CT | 32,282 | POUND | $0.0100 | $0.0100 | |
| 4 | 40600370 | LONG JOINT SEALANT | 15,952 | FOOT | $3.13 | $3.00 | |
| 5 | 40600990 | TEMPORARY RAMP | 1,323 | SQ YD | $0.0100 | $6.50 | |
| 6 | 40603085 | HMA BC IL-19.0 N70 | 5,036 | TON | $81.24 | $85.00 | |
| 7 | 40604062 | HMA SC IL-9.5 D N70 | 3,406 | TON | $106.03 | $95.00 | |
| 8 | 40800050 | INCIDENTAL HMA SURF | 133 | TON | $191.68 | $250.00 | |
| 9 | 44000155 | HMA SURF REM 1 1/2 | 26,819 | SQ YD | $2.03 | $2.60 | |
| 10 | 44000164 | HMA SURF REM 3 3/4 | 20,432 | SQ YD | $3.66 | $4.40 | |
| 11 | 44200050 | WELDED WIRE REINF | 464 | SQ YD | $17.44 | $10.00 | |
| 12 | 44201385 | CL C PATCH T1 13 | 14 | SQ YD | $180.00 | $220.00 | |
| 13 | 44201389 | CL C PATCH T2 13 | 500 | SQ YD | $177.00 | $220.00 | |
| 14 | 44201394 | CL C PATCH T3 13 | 248 | SQ YD | $174.00 | $215.00 | |
| 15 | 44201396 | CL C PATCH T4 13 | 217 | SQ YD | $170.00 | $210.00 | |
| 16 | 48102100 | AGG WEDGE SHLD TYPE B | 429 | TON | $43.79 | $45.00 | |
| 17 | 48203100 | HMA SHOULDERS | 1,531 | TON | $92.99 | $134.00 | |
| 18 | 63000001 | SPBGR TY A 6FT POSTS | 237.5 | FOOT | $39.90 | $65.00 | |
| 19 | 63000003 | SPBGR TY A 9FT POSTS | 3,000 | FOOT | $44.75 | $55.00 | |
| 20 | 63000019 | NON-BLOCKED SPBGR 6FT P | 317.2 | FOOT | $68.25 | $59.00 | |
| 21 | 63000030 | SPGR ATT TO CULVERT | 125 | FOOT | $357.00 | $422.00 | |
| 22 | 63000050 | WPGR ATT CLVRT CASE 1 | 100 | FOOT | $236.25 | $310.00 | |
| 23 | 63100045 | TRAF BAR TERM T2 | 8 | EACH | $1,942.50 | $2,450.00 | |
| 24 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $6,258.00 | $5,900.00 | |
| 25 | 63100167 | TR BAR TRM T1 SPL TAN | 12 | EACH | $4,725.00 | $3,825.00 | |
| 26 | 63200310 | GUARDRAIL REMOV | 4,059 | FOOT | $6.83 | $6.25 | |
| 27 | 64200108 | SHOULDER RUM STRIP 8 | 15,402 | FOOT | $0.4100 | $0.4500 | |
| 28 | 67000400 | ENGR FIELD OFFICE A | 10 | CAL MO | $1,800.00 | $1,400.00 | |
| 29 | 67100100 | MOBILIZATION | 1 | L SUM | $151,089.05 | $100,000.00 | |
| 30 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $37,040.02 | $5,000.00 | |
| 31 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $11,546.59 | $7,000.00 | |
| 32 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $2,000.00 | |
| 33 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.0100 | $1,000.00 | |
| 34 | 70103815 | TR CONT SURVEILLANCE | 15 | CAL DA | $0.0100 | $0.0100 | |
| 35 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $40.50 | $125.00 | |
| 36 | 70300100 | SHORT TERM PAVT MKING | 4,112 | FOOT | $1.53 | $1.50 | |
| 37 | 70300150 | SHRT TRM PAVT MK REM | 1,448 | SQ FT | $0.0100 | $2.50 | |
| 38 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 33,087 | FOOT | $0.0100 | $0.0100 | |
| 39 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 104 | FOOT | $0.0100 | $0.0100 | |
| 40 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 96 | FOOT | $0.0100 | $0.0100 | |
| 41 | 72501000 | TERMINAL MARKER - DA | 12 | EACH | $52.50 | $50.00 | |
| 42 | 78000200 | THPL PVT MK LINE 4 | 33,087 | FOOT | $0.8100 | $0.9000 | |
| 43 | 78000600 | THPL PVT MK LINE 12 | 104 | FOOT | $2.47 | $2.75 | |
| 44 | 78000650 | THPL PVT MK LINE 24 | 96 | FOOT | $5.25 | $5.75 | |
| 45 | 78100100 | RAISED REFL PAVT MKR | 206 | EACH | $40.95 | $44.00 | |
| 46 | 78200005 | GRDRAIL REF TYPE A | 52 | EACH | $10.50 | $12.00 | |
| 47 | 78300200 | RAISED REF PVT MK REM | 81 | EACH | $12.19 | $13.00 | |
| 48 | 78300201 | PAVMT MRKG REM GRIND | 11,333 | SQ FT | $0.0100 | $0.0100 |