D9 REST AREA PATCH 2022-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $702,322 | ||
| 2 | Kinney Contractors, Inc. | $727,788 | +3.6% | |
| 3 | G. M. Sipes Construction, Inc. | $899,100 | +28.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Kinney Contract… | #3 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $7,203.94 | $8,000.00 | $36,000.00 | |
| 2 | 20200600 | EXC & GR EX SHOULDER | 20 | UNIT | $1,057.05 | $900.00 | $250.00 | |
| 3 | 31100910 | SUB GRAN MAT A 12 | 1,842 | SQ YD | $32.77 | $35.00 | $15.00 | |
| 4 | 44004250 | PAVED SHLD REMOVAL | 1,104 | SQ YD | $27.73 | $20.00 | $10.00 | |
| 5 | 44200050 | WELDED WIRE REINF | 2,663 | SQ YD | $13.91 | $12.00 | $10.00 | |
| 6 | 44200966 | CL B PATCH T1 10 | 14 | SQ YD | $200.00 | $175.00 | $290.00 | |
| 7 | 44200970 | CL B PATCH T2 10 | 921 | SQ YD | $130.00 | $156.00 | $240.00 | |
| 8 | 44200974 | CL B PATCH T3 10 | 153 | SQ YD | $125.00 | $151.00 | $240.00 | |
| 9 | 44200976 | CL B PATCH T4 10 | 669 | SQ YD | $120.00 | $145.00 | $240.00 | |
| 10 | 44201299 | DOWEL BARS 1 1/2 | 2,515 | EACH | $20.34 | $24.00 | $15.00 | |
| 11 | 44213200 | SAW CUTS | 8,267 | FOOT | $6.28 | $0.5000 | $5.75 | |
| 12 | 44213204 | TIE BARS 3/4 | 1,021 | EACH | $15.13 | $16.00 | $10.00 | |
| 13 | 48300500 | PCC SHOULDERS 10 | 1,842 | SQ YD | $87.26 | $99.00 | $125.00 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $26,194.98 | $41,500.00 | $44,000.00 | |
| 15 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $14,270.61 | $7,000.00 | $0.0100 | |
| 16 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $82.33 | $120.00 | $25.00 | |
| 17 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $2,000.00 | $2,000.00 | $0.0100 |