116CR-1
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Piney Creek Construction & Repair Low bidder | $41,631 | ||
| 2 | E. T. Simonds Construction Company | $48,193 | +15.8% | |
| 3 | Samron Midwest Contracting, Inc. | $50,814 | +22.1% | |
| 4 | Mott Excavating, Inc. | $83,352 | +100.2% | |
| 5 | Sierra Bravo Contractors, LLC | $84,437 | +102.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Piney Creek Con… | #2 E. T. Simonds C… | #3 Samron Midwest … | #4 Mott Excavating… | #5 Sierra Bravo Co… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X5010523 | REM CONC END SEC | 2 | EACH | $242.10 | $180.21 | $850.00 | $325.00 | $1,483.56 | |
| 2 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $4,436.22 | $3,809.62 | $4,600.00 | $569.00 | $3,471.28 | |
| 3 | 20800150 | TRENCH BACKFILL | 25 | CU YD | $22.75 | $21.91 | $50.00 | $110.00 | $0.0100 | |
| 4 | 25000200 | SEEDING CL 2 | 0.1 | ACRE | $8,287.84 | $14,018.40 | $6,500.00 | $24,000.00 | $21,280.00 | |
| 5 | 25000400 | NITROGEN FERT NUTR | 0.5 | POUND | $19.80 | $22.00 | $6.00 | $600.00 | $1.54 | |
| 6 | 25000500 | PHOSPHORUS FERT NUTR | 0.5 | POUND | $19.80 | $22.00 | $6.00 | $600.00 | $1.54 | |
| 7 | 25000600 | POTASSIUM FERT NUTR | 0.5 | POUND | $19.80 | $22.00 | $6.00 | $600.00 | $1.54 | |
| 8 | 25000700 | AGR GROUND LIMESTONE | 0.1 | TON | $88.00 | $55.00 | $1,200.00 | $500.00 | $325.85 | |
| 9 | 25100630 | EROSION CONTR BLANKET | 27 | SQ YD | $1.65 | $53.29 | $25.00 | $15.00 | $46.55 | |
| 10 | 28000250 | TEMP EROS CONTR SEED | 0.5 | POUND | $0.0100 | $288.40 | $0.00 | $110.00 | $0.0100 | |
| 11 | 28100107 | STONE RIPRAP CL A4 | 4 | SQ YD | $146.07 | $38.44 | $100.00 | $340.00 | $367.72 | |
| 12 | 28200200 | FILTER FABRIC | 4 | SQ YD | $3.30 | $0.9900 | $25.00 | $110.00 | $33.25 | |
| 13 | 42000060 | WELDED WIRE REINF | 28 | SQ YD | $13.16 | $7.57 | $40.00 | $90.00 | $23.75 | |
| 14 | 42000501 | PCC PVT 10 JOINTED | 28 | SQ YD | $162.71 | $195.21 | $200.00 | $268.00 | $513.59 | |
| 15 | 44000100 | PAVEMENT REM | 28 | SQ YD | $22.64 | $23.72 | $55.00 | $80.00 | $188.30 | |
| 16 | 48100700 | AGGREGATE SHLDS A 8 | 7 | SQ YD | $44.70 | $23.67 | $90.00 | $88.00 | $101.83 | |
| 17 | 50105220 | PIPE CULVERT REMOV | 48 | FOOT | $18.10 | $74.30 | $40.00 | $11.00 | $95.99 | |
| 18 | 542A0241 | P CUL CL A 1 36 | 44 | FOOT | $123.83 | $154.22 | $185.00 | $151.00 | $357.84 | |
| 19 | 54213681 | PRC FLAR END SEC 36 | 2 | EACH | $2,086.54 | $2,144.95 | $2,200.00 | $2,300.00 | $3,394.34 | |
| 20 | 54247170 | GRATING-C FL END S 36 | 2 | EACH | $1,607.78 | $2,007.50 | $2,100.00 | $1,880.00 | $3,013.27 | |
| 21 | 67000400 | ENGR FIELD OFFICE A | 1 | CAL MO | $2,750.00 | $3,000.00 | $950.00 | $1,870.00 | $3,325.00 | |
| 22 | 67100100 | MOBILIZATION | 1 | L SUM | $7,460.80 | $5,636.60 | $3,000.00 | $4,000.00 | $5,066.24 | |
| 23 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $2,829.02 | $3,994.66 | $5,000.00 | $4,231.00 | $2,886.08 | |
| 24 | 70103815 | TR CONT SURVEILLANCE | 3 | CAL DA | $0.0100 | $0.0100 | $0.00 | $620.00 | $549.45 | |
| 25 | 70107025 | CHANGEABLE MESSAGE SN | 34 | CAL DA | $31.50 | $38.05 | $115.00 | $100.00 | $106.40 | |
| 26 | 78001110 | PAINT PVT MK LINE 4 | 30 | FOOT | $31.50 | $40.15 | $30.00 | $1,000.00 | $74.44 |