41N-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $183,441 | ||
| 2 | E. T. Simonds Construction Company | $183,442 | +0.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $15,000.00 | $15,797.26 | |
| 2 | X7030005 | TEMP PAVT MKING REMOV | 833 | SQ FT | $0.00 | $0.00 | |
| 3 | X7830070 | GRV RCSD PVT MRKG 5 | 63 | FOOT | $2.50 | $8.80 | |
| 4 | X7830074 | GRV RCSD PVT MRKG 7 | 413 | FOOT | $3.50 | $12.10 | |
| 5 | X7830078 | GRV RCSD PVT MRKG 13 | 285 | FOOT | $4.50 | $24.20 | |
| 6 | X7830090 | GRV RCSD PVT MRKG 25 | 67 | FOOT | $9.45 | $48.40 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,000.00 | $4,950.00 | |
| 8 | 20800150 | TRENCH BACKFILL | 6 | CU YD | $45.00 | $41.73 | |
| 9 | 42000501 | PCC PVT 10 JOINTED | 736 | SQ YD | $100.00 | $100.64 | |
| 10 | 42001300 | PROTECTIVE COAT | 736 | SQ YD | $0.00 | $0.00 | |
| 11 | 42400100 | PC CONC SIDEWALK 4 | 391 | SQ FT | $20.00 | $15.21 | |
| 12 | 42400800 | DETECTABLE WARNINGS | 36 | SQ FT | $25.00 | $30.39 | |
| 13 | 44000100 | PAVEMENT REM | 762 | SQ YD | $25.00 | $15.27 | |
| 14 | 44000500 | COMB CURB GUTTER REM | 57 | FOOT | $15.00 | $19.37 | |
| 15 | 44000600 | SIDEWALK REM | 220 | SQ FT | $10.00 | $5.02 | |
| 16 | 44201299 | DOWEL BARS 1 1/2 | 467 | EACH | $30.00 | $0.00 | |
| 17 | 44213204 | TIE BARS 3/4 | 171 | EACH | $15.00 | $14.32 | |
| 18 | 550A0380 | STORM SEW CL A 2 18 | 26 | FOOT | $125.00 | $89.34 | |
| 19 | 55100900 | STORM SEWER REM 18 | 6.5 | FOOT | $0.00 | $110.90 | |
| 20 | 60218500 | MAN TA 4 DIA T3F&G | 1 | EACH | $4,200.00 | $4,124.36 | |
| 21 | 60240220 | INLETS TB T3F&G | 1 | EACH | $4,100.00 | $2,077.61 | |
| 22 | 60500060 | REMOV INLETS | 1 | EACH | $350.00 | $720.88 | |
| 23 | 60603800 | COMB CC&G TB6.12 | 67 | FOOT | $45.00 | $75.31 | |
| 24 | 67000400 | ENGR FIELD OFFICE A | 1 | CAL MO | $1,000.00 | $2,000.00 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $11,000.00 | $14,301.32 | |
| 26 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $85.00 | $79.77 | |
| 27 | 70300100 | SHORT TERM PAVT MKING | 833 | FOOT | $0.00 | $0.00 | |
| 28 | 70300150 | SHRT TRM PAVT MK REM | 651.5 | SQ FT | $0.00 | $0.00 | |
| 29 | 70300220 | TEMP PVT MK LINE 4 | 63 | FOOT | $0.00 | $0.00 | |
| 30 | 70300240 | TEMP PVT MK LINE 6 | 413 | FOOT | $0.00 | $0.00 | |
| 31 | 70300260 | TEMP PVT MK LINE 12 | 285 | FOOT | $0.00 | $0.00 | |
| 32 | 70300280 | TEMP PVT MK LINE 24 | 67 | FOOT | $0.00 | $0.00 | |
| 33 | 78008210 | POLYUREA PM T1 LN 4 | 63 | FOOT | $5.50 | $8.05 | |
| 34 | 78008230 | POLYUREA PM T1 LN 6 | 413 | FOOT | $8.00 | $12.08 | |
| 35 | 78008250 | POLYUREA PM T1 LN 12 | 285 | FOOT | $17.00 | $24.16 | |
| 36 | 78008270 | POLYUREA PM T1 LN 24 | 67 | FOOT | $40.00 | $48.31 | |
| 37 | 78300201 | PAVMT MRKG REM GRIND | 33 | SQ FT | $5.50 | $5.50 |