Bid tab 78646

Let Mar 8, 2019 · District 9 · Perry Start free trial

‹ Mar 2019 results

D9 BRIDGE REPAIR 2019-3

Let date
Friday, March 8, 2019
Contract
78646 · job page
District
District 9
County
Perry
Highway
Limits
Bearm end repairs and joint replacement on SN 073-0033 carrying US 51 over ICG Railroad.

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Samron Midwest Contracting, Inc. Low bidder $218,060
2 Keeley & Sons, Inc. $221,063 +1.4%
3 E. T. Simonds Construction Company $242,678 +11.3%
4 The Kilian Corporation $262,935 +20.6%
5 Plocher Construction Company, Inc. $296,417 +35.9%

Bid tab: unit prices 16 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Samron Midwest …#2 Keeley & Sons, …#3 E. T. Simonds C…#4 The Kilian Corp…#5 Plocher Constru…
1X0325748 ACRYLIC COATING137SQ YD $70.00 $29.80 $83.78 $84.00 $79.00
2X0325749 FIBER WRAP1,236SQ FT $50.00 $47.80 $74.04 $41.00 $37.00
3Z0043800 P P CONC I-BM REPAIR20SQ FT $600.00 $1,497.80 $614.18 $1,090.00 $1,040.00
4Z0048665 RR PROT LIABILITY INS1L SUM $7,500.00 $5,980.00 $9,350.00 $7,850.00 $4,000.00
550102400 CONC REM4CU YD $2,850.00 $3,980.00 $4,169.57 $4,800.00 $9,600.00
650300255 CONC SUP-STR4.2CU YD $2,650.00 $5,780.00 $5,650.23 $7,500.00 $9,100.00
750300300 PROTECTIVE COAT20SQ YD $50.00 $25.60 $9.11 $3.00 $39.00
850800205 REINF BARS, EPOXY CTD520POUND $6.00 $7.90 $5.85 $3.00 $10.00
950800515 BAR SPLICERS6EACH $75.00 $93.13 $104.87 $63.00 $100.00
1052000110 PREF JT STRIP SEAL96FOOT $200.00 $257.80 $283.91 $210.00 $141.00
1159000200 EPOXY CRACK INJECTION214FOOT $45.00 $57.30 $62.06 $62.00 $59.00
1267000400 ENGR FIELD OFFICE A4CAL MO $1,250.00 $3,500.00 $2,000.00 $2,000.00 $750.00
1367100100 MOBILIZATION1L SUM $55,000.00 $11,500.00 $8,425.74 $60,450.00 $67,500.00
1470100450 TRAF CONT-PROT 7012011L SUM $500.00 $365.00 $3,283.56 $1,425.00 $14,000.00
1570101830 TRAF CONT-PROT BLR 211L SUM $8,500.00 $11,000.00 $12,045.00 $13,000.00 $17,000.00
1670107025 CHANGEABLE MESSAGE SN28CAL DA $80.00 $96.90 $53.57 $75.00 $150.00