(104,13)N-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $261,463 | ||
| 2 | Sierra Bravo Contractors, LLC | $340,040 | +30.1% | |
| 3 | Samron Midwest Contracting, Inc. | $378,326 | +44.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Sierra Bravo Co… | #3 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|
| 1 | X7015005 | CHANGEABLE MESSAGE SN | 168 | CAL DA | $35.71 | $93.89 | $65.00 | |
| 2 | X7830060 | GRV RCSD PM LTR & SYM | 100 | SQ FT | $11.00 | $10.80 | $10.25 | |
| 3 | X7830070 | GRV RCSD PVT MRKG 5 | 221 | FOOT | $3.48 | $3.41 | $3.25 | |
| 4 | X7830078 | GRV RCSD PVT MRKG 13 | 155 | FOOT | $10.45 | $10.26 | $10.00 | |
| 5 | X7830090 | GRV RCSD PVT MRKG 25 | 304 | FOOT | $13.20 | $12.96 | $12.50 | |
| 6 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $6,050.00 | $4,320.00 | $5,000.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 329 | CU YD | $27.01 | $49.92 | $23.00 | |
| 8 | 35101100 | AGG BASE CSE A 12 | 1,701 | SQ YD | $18.05 | $21.16 | $17.00 | |
| 9 | 42000401 | PCC PVT 9 JOINTED | 1,653 | SQ YD | $74.00 | $86.70 | $115.00 | |
| 10 | 42001300 | PROTECTIVE COAT | 1,677 | SQ YD | $0.00 | $1.63 | $0.0100 | |
| 11 | 42400100 | PC CONC SIDEWALK 4 | 511 | SQ FT | $16.71 | $13.43 | $12.00 | |
| 12 | 42400800 | DETECTABLE WARNINGS | 32 | SQ FT | $33.00 | $20.30 | $40.00 | |
| 13 | 44000100 | PAVEMENT REM | 1,653 | SQ YD | $7.89 | $19.44 | $22.00 | |
| 14 | 44000300 | CURB REM | 30 | FOOT | $22.43 | $22.46 | $20.00 | |
| 15 | 44000500 | COMB CURB GUTTER REM | 102 | FOOT | $13.67 | $19.82 | $12.00 | |
| 16 | 44000600 | SIDEWALK REM | 522 | SQ FT | $3.32 | $2.58 | $5.00 | |
| 17 | 44201299 | DOWEL BARS 1 1/2 | 174 | EACH | $15.04 | $18.50 | $30.00 | |
| 18 | 44213204 | TIE BARS 3/4 | 140 | EACH | $9.69 | $16.09 | $25.00 | |
| 19 | 60255500 | MAN ADJUST | 1 | EACH | $433.51 | $1,112.04 | $950.00 | |
| 20 | 60600605 | CONC CURB TB | 30 | FOOT | $58.28 | $51.97 | $50.00 | |
| 21 | 60603800 | COMB CC&G TB6.12 | 60 | FOOT | $57.27 | $27.95 | $75.00 | |
| 22 | 60605000 | COMB CC&G TB6.24 | 42 | FOOT | $48.48 | $60.75 | $95.00 | |
| 23 | 67000400 | ENGR FIELD OFFICE A | 1 | CAL MO | $1,800.00 | $2,702.86 | $2,000.00 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $11,445.97 | $16,192.39 | $30,800.00 | |
| 25 | 70101830 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $3,262.96 | $2,619.00 | $2,500.00 | |
| 26 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.00 | $1,971.00 | $1,950.00 | |
| 27 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1,816.86 | $243.00 | $230.00 | |
| 28 | 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $0.00 | $866.29 | $1.00 | |
| 29 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $2,130.53 | $5,076.59 | $3,500.00 | |
| 30 | 72000100 | SIGN PANEL T1 | 193 | SQ FT | $26.57 | $22.95 | $22.00 | |
| 31 | 72000200 | SIGN PANEL T2 | 27 | SQ FT | $26.57 | $18.09 | $17.50 | |
| 32 | 78008200 | POLYUREA PM T1 LTR-SY | 100 | SQ FT | $22.00 | $21.60 | $21.00 | |
| 33 | 78008210 | POLYUREA PM T1 LN 4 | 687 | FOOT | $6.47 | $6.35 | $6.00 | |
| 34 | 78008250 | POLYUREA PM T1 LN 12 | 155 | FOOT | $19.43 | $19.07 | $18.00 | |
| 35 | 78008270 | POLYUREA PM T1 LN 24 | 152 | FOOT | $38.50 | $37.80 | $37.00 | |
| 36 | 78300200 | RAISED REF PVT MK REM | 10 | EACH | $12.55 | $44.80 | $50.00 |