9(I-3)
- Let date
- Friday, June 14, 2024
- Contract
- 78376 · job page
- District
- District 9
- County
- Hamilton
- Highway
- Limits
- Removal of SN 033-9900, pavement removal, curb and gutter removal, full-depth HMA pavement, Combination concrete curb and gutter, PCC sidewalk, storm sewer and tree removal on IL 14 from Pearl Street to Virginia Street in McLeansboro.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sierra Bravo Contractors, LLC Low bidder | $810,944 | ||
| 2 | Samron Midwest Contracting, Inc. | $866,866 | +6.9% | |
| 3 | E. T. Simonds Construction Company | $939,897 | +15.9% | |
| 4 | Kieffer Bros. Construction Co., Inc. | $1,123,702 | +38.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sierra Bravo Co… | #2 Samron Midwest … | #3 E. T. Simonds C… | #4 Kieffer Bros. C… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $23,892.50 | $16,389.36 | $23,633.75 | $28,567.00 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $11,330.00 | $16,000.00 | $16,390.00 | $29,150.00 | |
| 3 | 20100110 | TREE REMOV 6-15 | 426 | UNIT | $50.43 | $38.00 | $48.74 | $23.00 | |
| 4 | 20100210 | TREE REMOV OVER 15 | 228 | UNIT | $56.54 | $48.00 | $45.53 | $64.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 1,545 | CU YD | $7.53 | $23.00 | $18.50 | $24.00 | |
| 6 | 20201200 | REM & DISP UNS MATL | 488 | CU YD | $13.23 | $15.00 | $26.95 | $67.00 | |
| 7 | 20400800 | FURNISHED EXCAVATION | 530.47 | CU YD | $28.19 | $45.00 | $53.86 | $37.00 | |
| 8 | 20800150 | TRENCH BACKFILL | 695 | CU YD | $59.07 | $70.00 | $58.93 | $46.00 | |
| 9 | 25000210 | SEEDING CL 2A | 0.33 | ACRE | $9,270.00 | $9,200.00 | $8,965.00 | $10,494.00 | |
| 10 | 25000350 | SEEDING CL 7 | 0.33 | ACRE | $515.00 | $4,080.00 | $3,987.52 | $583.00 | |
| 11 | 25000400 | NITROGEN FERT NUTR | 60.06 | POUND | $4.12 | $2.00 | $1.76 | $4.66 | |
| 12 | 25000500 | PHOSPHORUS FERT NUTR | 30.03 | POUND | $4.12 | $2.00 | $1.76 | $4.66 | |
| 13 | 25000600 | POTASSIUM FERT NUTR | 30.03 | POUND | $4.12 | $2.00 | $1.76 | $4.66 | |
| 14 | 25000700 | AGR GROUND LIMESTONE | 0.67 | TON | $412.00 | $395.00 | $385.00 | $466.40 | |
| 15 | 25100115 | MULCH METHOD 2 | 0.67 | ACRE | $7,385.10 | $7,040.00 | $6,875.00 | $8,360.22 | |
| 16 | 28000250 | TEMP EROS CONTR SEED | 100.1 | POUND | $3.40 | $4.00 | $9.83 | $1.17 | |
| 17 | 28000400 | PERIMETER EROS BAR | 880 | FOOT | $3.51 | $4.00 | $5.43 | $4.37 | |
| 18 | 28000500 | INLET & PIPE PROTECT | 1 | EACH | $152.02 | $200.00 | $301.06 | $119.78 | |
| 19 | 28100707 | STONE DUMP RIP CL A4 | 4 | SQ YD | $150.19 | $190.00 | $221.82 | $186.14 | |
| 20 | 31100910 | SUB GRAN MAT A 12 | 1,450 | SQ YD | $22.47 | $30.00 | $73.33 | $30.48 | |
| 21 | 40600275 | BIT MATLS PR CT | 3,266 | POUND | $0.0100 | $1.16 | $0.0100 | $0.0100 | |
| 22 | 40600295 | P BIT MATLS TACK CT | 856 | POUND | $0.0100 | $0.7400 | $0.0100 | $0.0100 | |
| 23 | 40600370 | LONG JOINT SEALANT | 450 | FOOT | $30.59 | $30.41 | $29.70 | $34.63 | |
| 24 | 40604062 | HMA SC IL-9.5 D N70 | 10 | TON | $676.23 | $95.00 | $656.53 | $765.51 | |
| 25 | 40701901 | HMA PAVT FD 11 | 1,195 | SQ YD | $88.14 | $95.00 | $85.57 | $99.77 | |
| 26 | 42400200 | PC CONC SIDEWALK 5 | 4,210 | SQ FT | $13.01 | $10.00 | $13.89 | $14.73 | |
| 27 | 42400800 | DETECTABLE WARNINGS | 40 | SQ FT | $43.26 | $20.00 | $46.20 | $48.97 | |
| 28 | 44000100 | PAVEMENT REM | 473 | SQ YD | $12.44 | $45.00 | $24.42 | $37.63 | |
| 29 | 44000155 | HMA SURF REM 1 1/2 | 108 | SQ YD | $36.57 | $52.00 | $35.50 | $41.39 | |
| 30 | 44000500 | COMB CURB GUTTER REM | 104 | FOOT | $16.32 | $2.00 | $18.21 | $20.54 | |
| 31 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $59,104.63 | $50,000.00 | $28,624.37 | $40,868.30 | |
| 32 | 50100400 | REM EXIST STRUCT N2 | 1 | EACH | $7,542.74 | $7,500.00 | $5,719.62 | $9,603.60 | |
| 33 | 50104650 | SLOPE WALL REMOV | 54 | SQ YD | $23.29 | $62.00 | $25.66 | $30.48 | |
| 34 | 54001001 | BOX CUL END SEC C1 | 1 | EACH | $11,299.82 | $15,000.00 | $13,650.12 | $14,104.36 | |
| 35 | 54010402 | PCBC 4X2 | 35 | FOOT | $610.07 | $585.00 | $671.89 | $520.30 | |
| 36 | 542A0265 | P CUL CL A 1 60 | 217.8 | FOOT | $330.60 | $370.00 | $367.17 | $441.62 | |
| 37 | 54213705 | PRC FLAR END SEC 60 | 1 | EACH | $7,612.59 | $3,200.00 | $7,906.75 | $9,951.28 | |
| 38 | 550A0070 | STORM SEW CL A 1 15 | 266 | FOOT | $58.98 | $81.00 | $96.61 | $84.69 | |
| 39 | 550A0090 | STORM SEW CL A 1 18 | 138 | FOOT | $61.14 | $83.00 | $128.71 | $105.05 | |
| 40 | 550A0120 | STORM SEW CL A 1 24 | 334.7 | FOOT | $83.72 | $85.00 | $116.82 | $128.37 | |
| 41 | 55100700 | STORM SEWER REM 15 | 101 | FOOT | $16.86 | $12.00 | $19.07 | $24.70 | |
| 42 | 55100900 | STORM SEWER REM 18 | 113 | FOOT | $18.08 | $11.00 | $17.04 | $30.00 | |
| 43 | 55101200 | STORM SEWER REM 24 | 342 | FOOT | $17.92 | $8.00 | $22.52 | $36.46 | |
| 44 | 55102100 | STORM SEWER REM 60 | 216 | FOOT | $15.77 | $24.00 | $17.83 | $41.23 | |
| 45 | 60218500 | MAN TA 4 DIA T3F&G | 4 | EACH | $4,020.62 | $3,800.00 | $4,110.41 | $4,318.12 | |
| 46 | 60219000 | MAN TA 4 DIA T8G | 1 | EACH | $3,701.45 | $3,300.00 | $3,743.90 | $3,963.66 | |
| 47 | 60221000 | MAN TA 5 DIA T1F OL | 1 | EACH | $5,382.65 | $4,800.00 | $5,174.96 | $5,254.10 | |
| 48 | 60221200 | MAN TA 5 DIA T3F&G | 2 | EACH | $5,555.88 | $5,700.00 | $5,373.88 | $5,912.89 | |
| 49 | 60224454 | MAN TA 8 DIA T3F&G | 2 | EACH | $12,890.97 | $12,000.00 | $12,448.17 | $14,652.59 | |
| 50 | 60240220 | INLETS TB T3F&G | 3 | EACH | $3,635.97 | $3,200.00 | $3,822.59 | $2,248.47 | |
| 51 | 60500060 | REMOV INLETS | 12 | EACH | $681.07 | $270.00 | $557.60 | $278.25 | |
| 52 | 60605000 | COMB CC&G TY B-6.24 | 104 | FOOT | $77.25 | $105.00 | $78.12 | $87.45 | |
| 53 | 66900200 | NON SPL WASTE DISPOSL | 40 | CU YD | $70.87 | $100.00 | $49.23 | $174.11 | |
| 54 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,493.50 | $1,650.00 | $1,595.00 | $3,381.40 | |
| 55 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,266.00 | $2,500.00 | $2,420.00 | $2,915.00 | |
| 56 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,266.00 | $2,500.00 | $2,420.00 | $2,681.79 | |
| 57 | 66901006 | REG SUB MON | 2 | CAL DA | $1,364.75 | $1,500.00 | $1,457.50 | $3,264.80 | |
| 58 | 67000400 | ENGR FIELD OFFICE A | 11 | CAL MO | $2,108.06 | $1,700.00 | $2,000.00 | $3,993.55 | |
| 59 | 67100100 | MOBILIZATION | 1 | L SUM | $48,656.61 | $52,000.00 | $46,292.29 | $163,919.91 | |
| 60 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $83.99 | $135.00 | $87.26 | $139.92 | |
| 61 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 112 | FOOT | $0.0100 | $26.00 | $0.0100 | $26.82 | |
| 62 | 78001110 | PAINT PVT MK LINE 4 | 112 | FOOT | $21.08 | $26.00 | $22.52 | $26.82 | |
| 63 | 78100100 | RAISED REFL PAVT MKR | 12 | EACH | $343.63 | $200.00 | $366.98 | $389.00 | |
| 64 | 78300201 | PVT MKG REM GRINDING | 38 | SQ FT | $14.70 | $17.00 | $0.0100 | $17.20 |