(15, 16-1)PP
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $952,947 | ||
| 2 | G. M. Sipes Construction, Inc. | $961,906 | +0.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|
| 1 | X4406020 | PART DEP REM T1 2 | 353 | SQ YD | $58.00 | $52.66 | |
| 2 | X4406220 | PART DEP REM T2 2 | 471 | SQ YD | $57.00 | $52.39 | |
| 3 | X4406420 | PART DEP REM T3 2 | 372 | SQ YD | $56.00 | $51.66 | |
| 4 | X4406620 | PART DEP REM T4 2 | 701 | SQ YD | $55.00 | $50.66 | |
| 5 | X4421000 | PARTIAL DEPTH PATCH | 212 | TON | $560.00 | $542.67 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 7 | 44200050 | WELDED WIRE REINF | 499 | SQ YD | $20.00 | $10.00 | |
| 8 | 44200982 | CL B PATCH T2 11 | 1,372 | SQ YD | $235.00 | $280.00 | |
| 9 | 44200986 | CL B PATCH T3 11 | 291 | SQ YD | $232.00 | $275.00 | |
| 10 | 44200988 | CL B PATCH T4 11 | 208 | SQ YD | $230.00 | $275.00 | |
| 11 | 44201299 | DOWEL BARS 1 1/2 | 3,420 | EACH | $25.00 | $20.00 | |
| 12 | 44213200 | SAW CUTS | 11,049 | FOOT | $3.00 | $0.0100 | |
| 13 | 44213204 | TIE BARS 3/4 | 52 | EACH | $17.00 | $25.00 | |
| 14 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $4,000.00 | $1,500.00 | |
| 15 | 67100100 | MOBILIZATION | 1 | L SUM | $55,000.00 | $48,000.00 | |
| 16 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $16,000.00 | $15,000.00 | |
| 17 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $53,000.00 | $60,000.00 | |
| 18 | 70107025 | CHANGEABLE MESSAGE SN | 45 | CAL DA | $60.00 | $50.00 | |
| 19 | 70300100 | SHORT TERM PAVT MKING | 2,806 | FOOT | $2.00 | $3.76 | |
| 20 | 70300150 | SHRT TRM PAVT MK REM | 1,247 | SQ FT | $4.00 | $2.00 | |
| 21 | 78001110 | PAINT PVT MK LINE 4 | 2,806 | FOOT | $1.00 | $0.8500 | |
| 22 | 78300200 | RAISED REF PVT MK REM | 35 | EACH | $18.00 | $0.0100 |