Bid tab 76T23

Let Mar 8, 2024 · District 8 · Bond Sign up free

‹ Mar 2024 results

34Q

Let date
Friday, March 8, 2024
Contract
76T23 · job page
District
District 8
County
Bond
Highway
Limits
0.9 miles of resurfacing on State Street from O-Fallon Street to US 40 in Pocahontas.

Bidders 2

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 The Kilian Corporation Low bidder $257,173
2 Christ Bros. Asphalt, Inc. $271,576 +5.6%

Bid tab: unit prices 14 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 The Kilian Corp…#2 Christ Bros. As…
1X7810400 TEMP RAISED PAVT MKR62EACH $26.00 $81.29
240600290 BIT MATLS TACK CT3,971POUND $2.00 $1.90
340600370 LONG JOINT SEALANT4,963FOOT $3.85 $4.17
440600990 TEMPORARY RAMP60SQ YD $0.0100 $0.0100
540604052 HMA SC IL-9.5 C N70927TON $140.00 $144.00
644000155 HMA SURF REM 1 1/211,029SQ YD $4.55 $4.25
767100100 MOBILIZATION1L SUM $25,535.00 $23,448.00
870100460 TRAF CONT-PROT 7013061L SUM $2,500.00 $14,556.00
970102620 TR CONT & PROT 7015011L SUM $14,000.00 $14,556.00
1070300100 SHORT TERM PAVT MKING451FOOT $3.50 $3.77
1170300150 SHRT TRM PAVT MK REM150SQ FT $7.50 $0.0100
1270300221 TEMP PVT MK LINE 4 - PAINT13,942FOOT $0.0100 $0.0100
1378001120 PAINT PVT MK LINE 513,942FOOT $0.2600 $0.2500
1478300202 PVT MKG REM WTR BLAST4,647SQ FT $0.0100 $0.0100