(30,66,108,109,110,111)PP-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | The Kilian Corporation Low bidder | $738,089 | ||
| 2 | Christ Bros. Asphalt, Inc. | $748,076 | +1.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 The Kilian Corp… | #2 Christ Bros. As… |
|---|---|---|---|---|---|---|---|
| 1 | X4406030 | PART DEP REM T1 3 | 7 | SQ YD | $102.00 | $24.55 | |
| 2 | X4406230 | PART DEP REM T2 3 | 450 | SQ YD | $80.00 | $24.55 | |
| 3 | X4406430 | PART DEP REM T3 3 | 224 | SQ YD | $62.00 | $24.55 | |
| 4 | X4406630 | PART DEP REM T4 3 | 4,160 | SQ YD | $42.00 | $24.55 | |
| 5 | X4421000 | PARTIAL DEPTH PATCH | 810 | TON | $149.00 | $228.94 | |
| 6 | 44200050 | WELDED WIRE REINF | 520 | SQ YD | $18.50 | $15.00 | |
| 7 | 44201013 | CL B PATCH T4 13 | 520 | SQ YD | $148.00 | $140.00 | |
| 8 | 44201299 | DOWEL BARS 1 1/2 | 42 | EACH | $31.00 | $30.00 | |
| 9 | 44201798 | CL D PATCH T1 13 | 64 | SQ YD | $271.00 | $243.76 | |
| 10 | 44201803 | CL D PATCH T2 13 | 301 | SQ YD | $238.00 | $243.76 | |
| 11 | 44201807 | CL D PATCH T3 13 | 38 | SQ YD | $217.00 | $243.76 | |
| 12 | 44201809 | CL D PATCH T4 13 | 455 | SQ YD | $197.00 | $243.76 | |
| 13 | 44213200 | SAW CUTS | 310 | FOOT | $16.50 | $20.00 | |
| 14 | 44213204 | TIE BARS 3/4 | 80 | EACH | $18.50 | $15.00 | |
| 15 | 67100100 | MOBILIZATION | 1 | L SUM | $44,200.00 | $65,401.00 | |
| 16 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $60,615.00 | $4,000.00 | |
| 17 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $0.0100 | $45,121.00 | |
| 18 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $0.0100 | $10,828.00 | |
| 19 | 78001110 | PAINT PVT MK LINE 4 | 12,599 | FOOT | $0.4700 | $1.59 |