42-2DM-1
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stutz Excavating, Inc. Low bidder | $64,276 | ||
| 2 | Petroff Trucking Company, Inc. | $124,770 | +94.1% | |
| 3 | Freesen, a div of UCM, Inc. | $150,926 | +134.8% | |
| 4 | Phoenix Corporation of the Quad Cities | $157,220 | +144.6% | |
| 5 | Gibbs Construction | $341,720 | +431.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stutz Excavatin… | #2 Petroff Truckin… | #3 Freesen, a div … | #4 Phoenix Corpora… | #5 Gibbs Construct… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $6,500.00 | $9,259.00 | $17,572.06 | $13,500.00 | $20,000.00 | |
| 2 | Z0007602 | BLDG REMOV NO 2 | 1 | L SUM | $1,500.00 | $11,832.00 | $4,732.51 | $14,500.00 | $43,000.00 | |
| 3 | Z0007603 | BLDG REMOV NO 3 | 1 | L SUM | $3,000.00 | $14,158.00 | $10,345.06 | $24,500.00 | $30,000.00 | |
| 4 | Z0007604 | BLDG REMOV NO 4 | 1 | L SUM | $250.00 | $4,138.00 | $2,806.28 | $500.00 | $11,000.00 | |
| 5 | Z0007605 | BLDG REMOV NO 5 | 1 | L SUM | $500.00 | $1,990.00 | $4,022.86 | $1,500.00 | $11,000.00 | |
| 6 | Z0007606 | BLDG REMOV NO 6 | 1 | L SUM | $8,500.00 | $14,920.00 | $25,850.00 | $24,500.00 | $50,000.00 | |
| 7 | Z0007607 | BLDG REMOV NO 7 | 1 | L SUM | $1,000.00 | $4,760.00 | $3,850.00 | $3,500.00 | $17,000.00 | |
| 8 | Z0007608 | BLDG REMOV NO 8 | 1 | L SUM | $2,500.00 | $4,520.00 | $5,612.56 | $1,600.00 | $8,000.00 | |
| 9 | Z0015500 | DEBRIS REMOVAL | 1 | L SUM | $2,000.00 | $5,500.00 | $11,590.26 | $6,650.00 | $20,000.00 | |
| 10 | Z0023800 | FILL EX SEPTIC TANK | 2 | EACH | $500.00 | $3,000.00 | $1,271.81 | $1,000.00 | $3,000.00 | |
| 11 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $4,000.00 | $5,000.00 | $4,868.84 | $6,500.00 | $6,000.00 | |
| 12 | Z0049901 | R&D NON-FR ASB BLD 1 | 1 | L SUM | $4,500.00 | $5,500.00 | $5,775.00 | $3,300.00 | $18,000.00 | |
| 13 | Z0049906 | R&D NON-FR ASB BLD 6 | 1 | L SUM | $3,500.00 | $4,500.00 | $2,475.00 | $3,300.00 | $18,000.00 | |
| 14 | 25000110 | SEEDING CL 1A | 0.75 | ACRE | $2,400.00 | $2,500.00 | $3,300.00 | $3,500.00 | $5,000.00 | |
| 15 | 25000400 | NITROGEN FERT NUTR | 67.5 | POUND | $3.65 | $5.00 | $5.50 | $8.00 | $8.00 | |
| 16 | 25000500 | PHOSPHORUS FERT NUTR | 67.5 | POUND | $3.65 | $5.00 | $5.50 | $8.00 | $8.00 | |
| 17 | 25000600 | POTASSIUM FERT NUTR | 67.5 | POUND | $3.65 | $5.00 | $5.50 | $8.00 | $8.00 | |
| 18 | 25000700 | AGR GROUND LIMESTONE | 1.5 | TON | $600.00 | $700.00 | $770.00 | $980.00 | $1,000.00 | |
| 19 | 25100115 | MULCH METHOD 2 | 1.5 | ACRE | $2,175.00 | $1,600.00 | $1,650.00 | $2,500.00 | $3,000.00 | |
| 20 | 28000250 | TEMP EROS CONTR SEED | 75 | POUND | $15.00 | $5.00 | $7.11 | $3.00 | $10.00 | |
| 21 | 28000400 | PERIMETER EROS BAR | 1,160 | FOOT | $5.15 | $3.00 | $6.02 | $3.00 | $10.00 | |
| 22 | 67100100 | MOBILIZATION | 1 | L SUM | $4,225.00 | $8,000.00 | $25,896.49 | $17,200.00 | $20,000.00 | |
| 23 | 67201000 | SEAL ABAN WATER WELLS | 5 | EACH | $1,500.00 | $2,900.00 | $1,650.00 | $4,200.00 | $8,000.00 |