60-8PS-2
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stutz Excavating, Inc. Low bidder | $54,536 | ||
| 2 | Haier Plumbing and Heating, Inc. | $69,959 | +28.3% | |
| 3 | RCS Construction, Inc. | $88,728 | +62.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stutz Excavatin… | #2 Haier Plumbing … | #3 RCS Constructio… |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0054517 | ROCK FILL - FOUNDATN | 12 | TON | $60.00 | $95.00 | $90.00 | |
| 2 | 20700220 | POROUS GRAN EMBANK | 46 | CU YD | $50.00 | $89.30 | $110.00 | |
| 3 | 28100107 | STONE RIPRAP CL A4 | 80 | SQ YD | $107.00 | $36.20 | $65.00 | |
| 4 | 28200200 | FILTER FABRIC | 80 | SQ YD | $9.50 | $10.80 | $7.00 | |
| 5 | 50102400 | CONC REM | 14.5 | CU YD | $200.00 | $315.86 | $300.00 | |
| 6 | 50200450 | REM/DISP UNS MATL-STR | 6 | CU YD | $125.00 | $423.33 | $150.00 | |
| 7 | 50800105 | REINFORCEMENT BARS | 4,240 | POUND | $2.40 | $2.83 | $3.00 | |
| 8 | 52200020 | TEMP SOIL RETEN SYSTM | 31 | SQ FT | $100.00 | $0.0100 | $150.00 | |
| 9 | 54003000 | CONC BOX CUL | 19.7 | CU YD | $1,100.00 | $1,473.67 | $975.00 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $3,600.00 | $12,800.00 | $35,000.00 |