126-SW-1
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Hank's Excavating & Landscaping, Inc. Low bidder | $151,631 | ||
| 2 | Kinney Contractors, Inc. | $152,888 | +0.8% | |
| 3 | Keller Construction, Inc. | $174,852 | +15.3% | |
| 4 | Stutz Excavating, Inc. | $207,509 | +36.9% | |
| 5 | Guinzy Construction,Inc. | $247,289 | +63.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Hank's Excavati… | #2 Kinney Contract… | #3 Keller Construc… | #4 Stutz Excavatin… | #5 Guinzy Construc… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327979 | PAVMT MRKG REM GRIND | 654 | SQ FT | $5.95 | $6.00 | $1.05 | $5.95 | $6.88 | |
| 2 | X6660445 | ROW/PROPERTY CORNERS | 1 | EACH | $1,155.00 | $500.00 | $1,155.00 | $2,500.00 | $1,217.48 | |
| 3 | X7030005 | TEMP PAVT MKING REMOV | 654 | SQ FT | $0.0100 | $6.00 | $5.95 | $5.95 | $6.88 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $1,800.00 | $4,000.00 | $2,000.00 | $7,500.00 | $14,001.05 | |
| 5 | 25000200 | SEEDING CL 2 | 0.25 | ACRE | $11,400.00 | $12,000.00 | $7,476.00 | $7,500.00 | $8,668.48 | |
| 6 | 25000400 | NITROGEN FERT NUTR | 23 | POUND | $1.21 | $2.00 | $13.85 | $14.00 | $16.07 | |
| 7 | 25000500 | PHOSPHORUS FERT NUTR | 23 | POUND | $1.21 | $2.00 | $13.85 | $14.00 | $16.07 | |
| 8 | 25000600 | POTASSIUM FERT NUTR | 23 | POUND | $1.21 | $2.00 | $13.85 | $14.00 | $16.07 | |
| 9 | 42400100 | PC CONC SIDEWALK 4 | 2,613 | SQ FT | $11.75 | $15.50 | $17.40 | $24.90 | $24.36 | |
| 10 | 42400800 | DETECTABLE WARNINGS | 304 | SQ FT | $57.00 | $30.00 | $28.80 | $24.00 | $33.27 | |
| 11 | 44000500 | COMB CURB GUTTER REM | 226 | FOOT | $51.35 | $18.50 | $26.30 | $34.80 | $128.75 | |
| 12 | 44000600 | SIDEWALK REM | 2,682 | SQ FT | $3.00 | $3.00 | $4.35 | $10.00 | $9.88 | |
| 13 | 44201299 | DOWEL BARS 1 1/2 | 46 | EACH | $52.00 | $40.00 | $20.50 | $10.00 | $11.35 | |
| 14 | 60603500 | COMB CC&G TB6.06 | 29 | FOOT | $127.70 | $75.00 | $110.00 | $60.00 | $265.38 | |
| 15 | 60605000 | COMB CC&G TB6.24 | 198 | FOOT | $132.00 | $80.00 | $57.95 | $63.40 | $71.94 | |
| 16 | 66900200 | NON SPL WASTE DISPOSL | 5 | CU YD | $124.00 | $10.00 | $230.00 | $295.00 | $413.94 | |
| 17 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,000.00 | $1,250.00 | $2,050.00 | $865.00 | $1,193.13 | |
| 18 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,200.00 | $2,250.00 | $3,045.00 | $2,625.00 | $2,556.71 | |
| 19 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,200.00 | $2,250.00 | $2,205.00 | $2,050.00 | $2,556.71 | |
| 20 | 66901006 | REG SUB MON | 3 | CAL DA | $820.00 | $825.00 | $2,100.00 | $945.00 | $949.64 | |
| 21 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $1,875.00 | $1,575.00 | $1,600.00 | $2,200.00 | $1,947.97 | |
| 22 | 67100100 | MOBILIZATION | 1 | L SUM | $1,100.00 | $9,300.00 | $25,000.00 | $15,000.00 | $2,045.37 | |
| 23 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $6,000.00 | $9,500.00 | $8,150.00 | $8,150.00 | $9,435.49 | |
| 24 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $7,050.00 | $1,500.00 | $1,217.48 | |
| 25 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $2,400.00 | $4,500.00 | $800.00 | $800.00 | $913.11 | |
| 26 | 70103815 | TR CONT SURVEILLANCE | 15 | CAL DA | $300.00 | $1.00 | $275.00 | $150.00 | $973.99 | |
| 27 | 70300260 | TEMP PVT MK LINE 12 | 654 | FOOT | $0.0100 | $9.50 | $2.65 | $9.60 | $11.14 | |
| 28 | 78000600 | THPL PVT MK LINE 12 | 654 | FOOT | $11.00 | $11.00 | $5.50 | $11.00 | $12.78 |