D7 BRIDGE REPAIRS 2025-12
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | William Charles Construction Company, LLC Low bidder | $1,412,000 | ||
| 2 | Samron Midwest Contracting, Inc. | $1,960,660 | +38.9% | |
| 3 | Sangamo Construction Company | $2,060,152 | +45.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 William Charles… | #2 Samron Midwest … | #3 Sangamo Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X5051204 | STRUCTURAL STL REMOVL | 6,140 | POUND | $10.00 | $55.00 | $79.56 | |
| 2 | X5051206 | STRUCT STEEL REPAIR | 38,800 | POUND | $30.00 | $30.00 | $35.27 | |
| 3 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,000.00 | $35,000.00 | $7,946.73 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $84,720.00 | $115,000.00 | $121,548.97 | |
| 5 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $41,880.00 | $125,000.00 | $36,618.18 | |
| 6 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $48,000.00 | $175,000.00 | $29,646.59 | |
| 7 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $125.00 | $160.00 | $132.45 |