D7 PATCHING 2024-2
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Earth Worx Solutions LLC Low bidder | $856,417 | ||
| 2 | Ramirez Diversified Services, LLC | $1,077,564 | +25.8% | |
| 3 | CSD Environmental Services, Inc. | $2,087,266 | +143.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Earth Worx Solu… | #2 Ramirez Diversi… | #3 CSD Environment… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4420563 | CL A PATCH T1 11 SPL | 192 | SQ YD | $262.00 | $295.00 | $1,650.00 | |
| 2 | X4420565 | CL A PATCH T2 11 SPL | 626.7 | SQ YD | $215.00 | $300.00 | $817.88 | |
| 3 | X4420569 | CL A PATCH T3 11 SPL | 108 | SQ YD | $203.00 | $305.00 | $794.81 | |
| 4 | X4420571 | CL A PATCH T4 11 SPL | 938.8 | SQ YD | $160.00 | $315.00 | $357.00 | |
| 5 | X4420581 | CL A PATCH T1 13 SPL | 4 | SQ YD | $400.00 | $340.00 | $3,094.00 | |
| 6 | X4420583 | CL A PATCH T2 13 SPL | 117.3 | SQ YD | $260.00 | $345.00 | $994.37 | |
| 7 | X4420585 | CL A PATCH T3 13 SPL | 32 | SQ YD | $235.00 | $350.00 | $994.37 | |
| 8 | X4420587 | CL A PATCH T4 13 SPL | 546.7 | SQ YD | $190.00 | $360.00 | $500.00 | |
| 9 | 44213000 | PATCH REINFORCEMENT | 2,565.5 | SQ YD | $60.00 | $11.00 | $78.50 | |
| 10 | 44213200 | SAW CUTS | 7,274 | FOOT | $6.00 | $9.50 | $9.10 | |
| 11 | 44213204 | TIE BARS 3/4 | 575 | EACH | $19.00 | $6.90 | $22.00 | |
| 12 | 67100100 | MOBILIZATION | 1 | L SUM | $50,500.00 | $72,000.00 | $86,398.67 | |
| 13 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $78,750.00 | $54,500.00 | $25,440.00 | |
| 14 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $3,500.00 | $2,500.00 | $150.00 | |
| 15 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $125.00 | $140.00 | $125.00 | |
| 16 | 88600100 | DET LOOP T1 | 200 | FOOT | $55.00 | $101.00 | $35.00 |