D7 BRIDGE REPAIRS 2025-4
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | C-Hill Civil Contractors, Inc. Low bidder | $369,369 | ||
| 2 | Howell Paving, Inc. | $391,468 | +6.0% | |
| 3 | Samron Midwest Contracting, Inc. | $396,409 | +7.3% | |
| 4 | Sangamo Construction Company | $437,963 | +18.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 C-Hill Civil Co… | #2 Howell Paving, … | #3 Samron Midwest … | #4 Sangamo Constru… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7016500 | TEMP BR TRAF SIG SPL | 1 | EACH | $22,000.00 | $12,000.00 | $15,000.00 | $27,132.85 | |
| 2 | Z0001800 | APPR SLAB REPAIR (PD) | 3 | SQ YD | $1,545.00 | $3,020.21 | $2,500.00 | $1,865.27 | |
| 3 | Z0012110 | BRD FLYASH/SLAG 2 1/4 | 162 | SQ YD | $345.00 | $335.79 | $285.00 | $335.39 | |
| 4 | Z0012130 | BR DECK SCAR 3/4 | 162 | SQ YD | $425.00 | $398.85 | $225.00 | $297.25 | |
| 5 | Z0016001 | DECK SLAB REP (FD-T1) | 6 | SQ YD | $2,650.00 | $3,148.92 | $3,000.00 | $2,667.19 | |
| 6 | Z0016002 | DECK SLAB REP (FD-T2) | 3 | SQ YD | $2,650.00 | $3,278.36 | $3,000.00 | $2,337.93 | |
| 7 | 20200500 | EARTH EXC WID | 75 | CU YD | $52.00 | $79.55 | $90.00 | $161.23 | |
| 8 | 35300300 | PCC BSE CSE 8 | 459 | SQ YD | $103.00 | $88.46 | $150.00 | $137.42 | |
| 9 | 40600290 | BIT MATLS TACK CT | 308 | POUND | $5.50 | $5.40 | $6.00 | $5.75 | |
| 10 | 40600982 | HMA SURF REM BUTT JT | 352 | SQ YD | $38.00 | $36.19 | $40.00 | $28.91 | |
| 11 | 40600990 | TEMPORARY RAMP | 56 | SQ YD | $26.25 | $27.15 | $100.00 | $82.14 | |
| 12 | 40604052 | HMA SC IL-9.5 C N70 | 58 | TON | $481.00 | $458.11 | $506.00 | $487.86 | |
| 13 | 44004250 | PAVED SHLD REMOVAL | 213 | SQ YD | $35.00 | $71.15 | $31.00 | $59.63 | |
| 14 | 50300260 | BR DECK GROOVING | 150 | SQ YD | $55.50 | $41.38 | $65.00 | $23.38 | |
| 15 | 50300300 | PROTECTIVE COAT | 162 | SQ YD | $5.50 | $21.32 | $7.00 | $3.97 | |
| 16 | 67000400 | ENGR FIELD OFFICE A | 5 | CAL MO | $2,100.00 | $3,323.56 | $2,500.00 | $3,385.71 | |
| 17 | 67100100 | MOBILIZATION | 1 | L SUM | $8,766.79 | $14,906.29 | $23,000.00 | $25,839.83 | |
| 18 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $15,700.00 | $25,554.86 | $25,000.00 | $34,108.54 | |
| 19 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $0.0100 | $4,450.29 | $0.0100 | $8,801.80 | |
| 20 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $2,800.00 | $7,650.54 | $5,000.00 | $1.00 | |
| 21 | 70107005 | PAVT MK BLKOUT TAPE 5 | 742 | FOOT | $3.25 | $4.66 | $4.00 | $6.76 | |
| 22 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $125.00 | $75.00 | $180.00 | $211.87 | |
| 23 | 70300150 | SHRT TRM PAVT MK REM | 309 | SQ FT | $3.30 | $6.51 | $4.00 | $6.95 | |
| 24 | 70400100 | TEMP CONC BARRIER | 350 | FOOT | $48.00 | $36.07 | $37.00 | $39.93 | |
| 25 | 70400200 | REL TEMP CONC BARRIER | 300 | FOOT | $9.50 | $7.31 | $6.00 | $10.46 | |
| 26 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $2,600.00 | $2,981.07 | $8,500.00 | $3,664.48 | |
| 27 | 70600260 | IMP ATTN TEMP FRN TL3 | 1 | EACH | $7,750.00 | $6,262.13 | $8,000.00 | $12,032.60 | |
| 28 | 70600350 | IMP ATTN REL NRD TL3 | 1 | EACH | $700.00 | $782.58 | $1,200.00 | $3,123.98 | |
| 29 | 78001110 | PAINT PVT MK LINE 4 | 1,544 | FOOT | $2.50 | $2.73 | $3.00 | $2.91 |