Bid tab 74C48

Let Apr 25, 2025 · District 7 · Effingham

‹ Apr 2025 results

D7 CRACK SEALING 2025-1

Let date
Friday, April 25, 2025
Contract
74C48 · job page
District
District 7
County
Effingham
Highway
Limits
20.9 miles of crack and joint sealing on southbound I-57 from the Clay County line to I-70 and on northbound I-57 from the Little Wabash River to I-70.
Classification
·
Project number

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Complete Asphalt Service Co. Low bidder $384,459
2 Denler, Inc. $397,899 +3.5%
3 Freehill Asphalt, Inc. $426,948 +11.1%
4 SKC Construction, Inc. $609,455 +58.5%

Bid tab: unit prices 6 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Complete Asphal…#2 Denler, Inc.#3 Freehill Asphal…#4 SKC Constructio…
145100100 CRACK ROUTING (PAVT)330,933FOOT $0.0100 $0.0100 $0.4600 $0.0200
245100200 CRACK FILLING99,280POUND $1.43 $1.64 $0.5300 $2.56
367100100 MOBILIZATION1L SUM $21,015.00 $12,000.00 $25,000.00 $70,000.00
470100420 TRAF CONT-PROT 7014114EACH $100.00 $1,500.00 $1.00 $330.00
570107025 CHANGEABLE MESSAGE SN28CAL DA $154.00 $100.00 $125.00 $155.00
678000400 THPL PVT MK LINE 6248,200FOOT $0.8600 $0.8500 $0.7800 $1.10