Bid tab 74A33

Let Mar 5, 2021 · District 7 · Cumberland Sign up free

‹ Mar 2021 results

D7 PATCHING 2021-3

Let date
Friday, March 5, 2021
Contract
74A33 · job page
District
District 7
County
Cumberland
Highway
Limits
Patching on IL 130 and the ramps at the ILL 130/I-70 interchange in Greenup; the project starts 0.1 miles north of Wagon Road and extends south for 0.7 miles to IL 121.

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Beniach Construction Co., Inc. Low bidder $354,380
2 Kinney Contractors, Inc. $363,904 +2.7%
3 Prado Construction $395,241 +11.5%
4 G. M. Sipes Construction, Inc. $431,473 +21.8%

Bid tab: unit prices 12 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Beniach Constru…#2 Kinney Contract…#3 Prado Construct…#4 G. M. Sipes Con…
144200050 WELDED WIRE REINF1,346SQ YD $13.00 $12.00 $9.94 $5.00
244201007 CL B PATCH T2 13249SQ YD $185.00 $185.00 $175.20 $245.00
344201011 CL B PATCH T3 1374SQ YD $183.00 $184.00 $242.94 $245.00
444201013 CL B PATCH T4 131,294SQ YD $182.00 $180.00 $184.70 $195.00
544201299 DOWEL BARS 1 1/2940EACH $12.00 $16.00 $22.12 $25.00
644213200 SAW CUTS3,863FOOT $0.00 $1.00 $3.40 $6.95
744213204 TIE BARS 3/4382EACH $8.00 $14.00 $17.62 $15.00
867100100 MOBILIZATION1L SUM $18,000.00 $10,000.00 $9,162.94 $21,000.00
970100450 TRAF CONT-PROT 7012011L SUM $3,131.00 $9,000.00 $16,295.48 $7,500.00
1070100825 TRAF CONT-PROT 7014561L SUM $3,500.00 $9,000.00 $9,604.56 $7,500.00
1170102635 TR CONT & PROT 7017011L SUM $0.00 $100.00 $2,704.98 $500.00
1270107025 CHANGEABLE MESSAGE SN28CAL DA $100.00 $100.00 $101.14 $25.00