D7 BRIDGE REPAIRS 2022-2
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Freesen, a div of UCM, Inc. Low bidder | $709,055 | ||
| 2 | Sangamo Construction Company | $777,555 | +9.7% | |
| 3 | Stark Excavating, Inc. | $867,780 | +22.4% | |
| 4 | White Construction LLC | $872,493 | +23.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Freesen, a div … | #2 Sangamo Constru… | #3 Stark Excavatin… | #4 White Construct… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $3,675.00 | $6,492.49 | $3,400.00 | $2,425.00 | |
| 2 | Z0001899 | JACK & REM EX BEARING | 12 | EACH | $2,801.24 | $2,768.33 | $1,550.00 | $2,500.00 | |
| 3 | Z0012111 | BRD FLYASH/SLAG 2 1/2 | 1,563 | SQ YD | $83.76 | $80.70 | $84.00 | $78.00 | |
| 4 | Z0012130 | BR DECK SCAR 3/4 | 1,563 | SQ YD | $35.14 | $36.80 | $40.00 | $58.00 | |
| 5 | Z0012754 | STR REP CON DP = < 5 | 205 | SQ FT | $183.44 | $220.90 | $160.00 | $165.00 | |
| 6 | Z0016001 | DECK SLAB REP (FD-T1) | 44 | SQ YD | $1,467.26 | $1,714.62 | $3,000.00 | $1,975.00 | |
| 7 | Z0016002 | DECK SLAB REP (FD-T2) | 26 | SQ YD | $1,247.27 | $1,100.10 | $2,700.00 | $1,600.00 | |
| 8 | 44000156 | HMA SURF REM 1 3/4 | 1,563 | SQ YD | $4.38 | $9.79 | $3.60 | $5.50 | |
| 9 | 50102400 | CONC REM | 24 | CU YD | $2,831.18 | $2,137.08 | $3,100.00 | $4,178.00 | |
| 10 | 50157300 | PROTECTIVE SHIELD | 616 | SQ YD | $50.23 | $73.53 | $80.00 | $73.00 | |
| 11 | 50300255 | CONC SUP-STR | 23.6 | CU YD | $2,822.61 | $2,743.18 | $3,600.00 | $3,375.00 | |
| 12 | 50300260 | BR DECK GROOVING | 1,545 | SQ YD | $7.85 | $6.84 | $7.10 | $6.50 | |
| 13 | 50300300 | PROTECTIVE COAT | 1,642 | SQ YD | $3.09 | $2.86 | $3.00 | $2.25 | |
| 14 | 50500405 | F & E STRUCT STEEL | 2,880 | POUND | $5.26 | $8.48 | $5.50 | $8.50 | |
| 15 | 50800205 | REINF BARS, EPOXY CTD | 4,510 | POUND | $2.35 | $4.81 | $2.80 | $2.80 | |
| 16 | 52000110 | PREF JT STRIP SEAL | 126 | FOOT | $264.94 | $245.98 | $252.00 | $320.00 | |
| 17 | 52100010 | ELAST BEARING ASSY T1 | 12 | EACH | $2,317.99 | $2,393.94 | $2,100.00 | $2,200.00 | |
| 18 | 52100520 | ANCHOR BOLTS 1 | 24 | EACH | $213.42 | $100.39 | $125.00 | $155.00 | |
| 19 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $2,848.44 | $1,724.34 | $2,700.00 | $2,400.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $18,323.97 | $45,875.72 | $52,750.00 | $52,000.00 | |
| 21 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $32,895.85 | $42,164.47 | $26,000.00 | $42,000.00 | |
| 22 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $131.25 | $157.99 | $130.00 | $126.75 | |
| 23 | 78001110 | PAINT PVT MK LINE 4 | 1,528 | FOOT | $2.24 | $3.51 | $3.40 | $2.13 |