(2,3)RS-3
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Ambraw Asphalt Materials, Inc. Low bidder | $3,711,052 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Ambraw Asphalt … |
|---|---|---|---|---|---|---|
| 1 | X0326440 | SURF REM VAR DP (SPL) | 2,598 | SQ YD | $5.80 | |
| 2 | X1200050 | BOX CULVERT REMOVAL | 31.3 | FOOT | $100.00 | |
| 3 | X4060995 | TEMPORARY RAMP SPL | 30 | SQ YD | $25.00 | |
| 4 | X4406675 | PART DEP REM T4 7.5 | 11,570 | SQ YD | $14.95 | |
| 5 | X4421000 | PARTIAL DEPTH PATCH | 4,860 | TON | $126.96 | |
| 6 | X7830090 | GRV RCSD PVT MRKG 25 | 56 | FOOT | $16.00 | |
| 7 | Z0004556 | HMA SURFACE RM (DECK) | 396 | SQ YD | $30.00 | |
| 8 | Z0005010 | HMA F PATCH (C M) | 1 | TON | $1,000.00 | |
| 9 | Z0016200 | DECK SLAB REP (PART) | 19 | SQ YD | $1,800.00 | |
| 10 | Z0033700 | LONG JOINT SEALANT | 31,069 | FOOT | $2.60 | |
| 11 | Z0049799 | PROT RESET SURVEY MRK | 5 | EACH | $650.00 | |
| 12 | Z0054505 | ROCK FILL - REPLACE | 11.2 | TON | $215.00 | |
| 13 | Z0070202 | SURVEY MARKER VAULT | 5 | EACH | $1,282.58 | |
| 14 | 20201200 | REM & DISP UNS MATL | 11.5 | CU YD | $105.00 | |
| 15 | 20700220 | POROUS GRAN EMBANK | 63.3 | CU YD | $100.00 | |
| 16 | 28100105 | STONE RIPRAP CL A3 | 34.2 | SQ YD | $95.00 | |
| 17 | 28200200 | FILTER FABRIC | 34.2 | SQ YD | $15.00 | |
| 18 | 40200800 | AGG SURF CSE B | 360 | TON | $22.00 | |
| 19 | 40600290 | BIT MATLS TACK CT | 57,984 | POUND | $0.6500 | |
| 20 | 40600990 | TEMPORARY RAMP | 1,090 | SQ YD | $25.00 | |
| 21 | 40602970 | HMA BC IL-9.5FG N70 | 8,419 | TON | $98.78 | |
| 22 | 40604052 | HMA SC IL-9.5 C N70 | 9,622 | TON | $95.64 | |
| 23 | 40800050 | INCIDENTAL HMA SURF | 367 | TON | $215.81 | |
| 24 | 44000155 | HMA SURF REM 1 1/2 | 77,135 | SQ YD | $1.95 | |
| 25 | 44000164 | HMA SURF REM 3 3/4 | 8,768 | SQ YD | $2.17 | |
| 26 | 44201815 | CL D PATCH T2 14 | 162 | SQ YD | $389.85 | |
| 27 | 44201819 | CL D PATCH T3 14 | 16 | SQ YD | $389.85 | |
| 28 | 44201821 | CL D PATCH T4 14 | 28 | SQ YD | $389.85 | |
| 29 | 48102100 | AGG WEDGE SHLD TYPE B | 1,344 | TON | $22.00 | |
| 30 | 50200100 | STRUCTURE EXCAVATION | 65.9 | CU YD | $45.00 | |
| 31 | 54010402 | PCBC 4X2 | 31.3 | FOOT | $1,330.00 | |
| 32 | 58100200 | WATERPRF MEMBRANE SYS | 396 | SQ YD | $144.43 | |
| 33 | 66700205 | PERM SURV MKRS T1 | 16 | EACH | $400.08 | |
| 34 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $798.06 | |
| 35 | 67000600 | ENGR FIELD LAB | 4 | CAL MO | $798.06 | |
| 36 | 67100100 | MOBILIZATION | 1 | L SUM | $198,306.32 | |
| 37 | 70100100 | TRAF CONT-PROT 701316 | 1 | EACH | $8,400.00 | |
| 38 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $44,962.00 | |
| 39 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $135,377.70 | |
| 40 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $23,000.00 | |
| 41 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $160.60 | |
| 42 | 70300100 | SHORT TERM PAVT MKING | 9,399 | FOOT | $1.00 | |
| 43 | 70300150 | SHRT TRM PAVT MK REM | 1,061 | SQ FT | $2.40 | |
| 44 | 70300220 | TEMP PVT MK LINE 4 | 88,187 | FOOT | $0.0100 | |
| 45 | 70300280 | TEMP PVT MK LINE 24 | 56 | FOOT | $0.0100 | |
| 46 | 78000650 | THPL PVT MK LINE 24 | 56 | FOOT | $14.00 | |
| 47 | 78001110 | PAINT PVT MK LINE 4 | 88,187 | FOOT | $0.1200 | |
| 48 | 78100100 | RAISED REFL PAVT MKR | 386 | EACH | $34.75 |