(21-Y,21-X)B-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sangamo Construction Company Low bidder | $3,233,083 | ||
| 2 | White Construction LLC | $3,579,000 | +10.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sangamo Constru… | #2 White Construct… |
|---|---|---|---|---|---|---|---|
| 1 | A2001016 | T-ACER RUBRM 2 | 10 | EACH | $396.62 | $375.00 | |
| 2 | A2007116 | T-QUERCUS RUBRA 2 | 45 | EACH | $396.61 | $375.00 | |
| 3 | B2001116 | T-CERCIS CAN TF 2 | 10 | EACH | $396.62 | $375.00 | |
| 4 | X4020500 | AGG SURF CSE B 6 | 205 | SQ YD | $15.46 | $30.00 | |
| 5 | X4401198 | HMA SURF REM VAR DP | 1,835 | SQ YD | $11.51 | $7.00 | |
| 6 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $24,128.31 | $10,000.00 | |
| 7 | X7030005 | TEMP PAVT MKING REMOV | 1,436 | SQ FT | $2.59 | $2.50 | |
| 8 | X7040125 | PIN TEMP CONC BARRIER | 54 | EACH | $25.28 | $80.00 | |
| 9 | Z0001900 | ASB BEARING PAD REMOV | 16 | EACH | $55.35 | $200.00 | |
| 10 | Z0004552 | APPROACH SLAB REM | 112 | SQ YD | $45.80 | $50.00 | |
| 11 | Z0004638 | PAVT BREAKING | 1,192 | SQ YD | $4.97 | $3.80 | |
| 12 | Z0005010 | HMA F PATCH (C M) | 1 | TON | $1,427.56 | $280.00 | |
| 13 | Z0046304 | P UNDR FOR STRUCT 4 | 329 | FOOT | $22.88 | $38.00 | |
| 14 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 15 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 16 | 20100110 | TREE REMOV 6-15 | 521 | UNIT | $28.78 | $40.00 | |
| 17 | 20100210 | TREE REMOV OVER 15 | 273 | UNIT | $59.96 | $45.00 | |
| 18 | 20200100 | EARTH EXCAVATION | 2,371 | CU YD | $25.42 | $20.00 | |
| 19 | 20200600 | EXC & GR EX SHOULDER | 20 | UNIT | $623.46 | $960.00 | |
| 20 | 20300100 | CHANNEL EXCAVATION | 494 | CU YD | $56.50 | $40.00 | |
| 21 | 20400800 | FURNISHED EXCAVATION | 479 | CU YD | $36.48 | $25.00 | |
| 22 | 20600200 | GRAN EMBANK SPEC | 1,230 | CU YD | $81.13 | $55.00 | |
| 23 | 25000200 | SEEDING CL 2 | 1.3 | ACRE | $3,172.92 | $3,000.00 | |
| 24 | 25000400 | NITROGEN FERT NUTR | 117 | POUND | $1.22 | $1.15 | |
| 25 | 25000500 | PHOSPHORUS FERT NUTR | 117 | POUND | $1.22 | $1.15 | |
| 26 | 25000600 | POTASSIUM FERT NUTR | 117 | POUND | $1.22 | $1.15 | |
| 27 | 25000700 | AGR GROUND LIMESTONE | 2.6 | TON | $259.12 | $245.00 | |
| 28 | 25100115 | MULCH METHOD 2 | 1.3 | ACRE | $1,903.75 | $1,800.00 | |
| 29 | 28000250 | TEMP EROS CONTR SEED | 390 | POUND | $4.32 | $10.00 | |
| 30 | 28000305 | TEMP DITCH CHECKS | 389 | FOOT | $17.69 | $17.00 | |
| 31 | 28000400 | PERIMETER EROS BAR | 2,451 | FOOT | $5.60 | $2.80 | |
| 32 | 28100109 | STONE RIPRAP CL A5 | 1,818 | SQ YD | $70.12 | $100.00 | |
| 33 | 28100207 | STONE RIPRAP CL A4 | 991 | TON | $67.89 | $90.00 | |
| 34 | 28200200 | FILTER FABRIC | 1,818 | SQ YD | $4.26 | $4.00 | |
| 35 | 35600716 | HMA BC WID 10 | 639 | SQ YD | $100.17 | $94.71 | |
| 36 | 40600275 | BIT MATLS PR CT | 2,811 | POUND | $0.8100 | $0.7700 | |
| 37 | 40600290 | BIT MATLS TACK CT | 2,322 | POUND | $0.5300 | $0.5000 | |
| 38 | 40600990 | TEMPORARY RAMP | 126 | SQ YD | $41.87 | $20.00 | |
| 39 | 40602970 | HMA BC IL-9.5FG N70 | 94 | TON | $211.26 | $199.75 | |
| 40 | 40603085 | HMA BC IL-19.0 N70 | 63 | TON | $287.40 | $271.74 | |
| 41 | 40604052 | HMA SC IL-9.5 C N70 | 260 | TON | $200.32 | $189.40 | |
| 42 | 40701901 | HMA PAVT FD 11 | 966 | SQ YD | $113.94 | $107.73 | |
| 43 | 42000060 | WELDED WIRE REINF | 357 | SQ YD | $21.09 | $30.00 | |
| 44 | 42000080 | PVT CON PCC BR APP SL | 357 | SQ YD | $190.73 | $185.00 | |
| 45 | 44000100 | PAVEMENT REM | 473 | SQ YD | $28.73 | $32.00 | |
| 46 | 44000155 | HMA SURF REM 1 1/2 | 1,722 | SQ YD | $9.87 | $4.00 | |
| 47 | 44004250 | PAVED SHLD REMOVAL | 484 | SQ YD | $39.07 | $20.00 | |
| 48 | 48101500 | AGGREGATE SHLDS B 6 | 1,180 | SQ YD | $21.97 | $17.00 | |
| 49 | 48102100 | AGG WEDGE SHLD TYPE B | 11 | TON | $91.05 | $75.00 | |
| 50 | 48203100 | HMA SHOULDERS | 400 | TON | $167.50 | $158.37 | |
| 51 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $69,803.84 | $80,000.00 | |
| 52 | 50100400 | REM EXIST STRUCT N2 | 1 | EACH | $54,487.21 | $75,000.00 | |
| 53 | 50105220 | PIPE CULVERT REMOV | 55 | FOOT | $19.18 | $15.00 | |
| 54 | 50200100 | STRUCTURE EXCAVATION | 120.8 | CU YD | $33.53 | $30.00 | |
| 55 | 50300100 | FLOOR DRAINS | 10 | EACH | $426.04 | $1,700.00 | |
| 56 | 50300225 | CONC STRUCT | 143.5 | CU YD | $864.68 | $1,200.00 | |
| 57 | 50300255 | CONC SUP-STR | 302.4 | CU YD | $1,681.80 | $1,500.00 | |
| 58 | 50300260 | BR DECK GROOVING | 1,229 | SQ YD | $9.71 | $9.20 | |
| 59 | 50300300 | PROTECTIVE COAT | 1,498 | SQ YD | $2.95 | $3.13 | |
| 60 | 50301350 | CONC SUPSTR APP SLAB | 251.4 | CU YD | $560.46 | $420.00 | |
| 61 | 50401105 | F & E P P CON I-BM 54 | 534 | FOOT | $469.14 | $600.00 | |
| 62 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $186,121.33 | $211,000.00 | |
| 63 | 50500505 | STUD SHEAR CONNECTORS | 1,692 | EACH | $5.27 | $4.84 | |
| 64 | 50800205 | REINF BARS, EPOXY CTD | 140,280 | POUND | $1.39 | $2.00 | |
| 65 | 50800515 | BAR SPLICERS | 573 | EACH | $45.04 | $40.00 | |
| 66 | 51201400 | FUR STL PILE HP10X42 | 1,356 | FOOT | $66.33 | $85.00 | |
| 67 | 51202305 | DRIVING PILES | 1,356 | FOOT | $0.0200 | $1.00 | |
| 68 | 51203400 | TEST PILE ST HP10X42 | 3 | EACH | $4,045.47 | $8,000.00 | |
| 69 | 51500100 | NAME PLATES | 2 | EACH | $585.97 | $500.00 | |
| 70 | 52100520 | ANCHOR BOLTS 1 | 24 | EACH | $83.89 | $90.00 | |
| 71 | 52200020 | TEMP SOIL RETEN SYSTM | 492 | SQ FT | $0.1000 | $150.00 | |
| 72 | 542D1075 | P CUL CL D 2 30 | 53 | FOOT | $86.28 | $130.00 | |
| 73 | 54262730 | METAL FL END SEC 30" | 2 | EACH | $1,128.16 | $1,600.00 | |
| 74 | 58600101 | GRANULAR BACKFILL STR | 418 | CU YD | $70.27 | $66.00 | |
| 75 | 59100100 | GEOCOMPOSITE WALL DR | 202 | SQ YD | $22.60 | $40.00 | |
| 76 | 63000001 | SPBGR TY A 6FT POSTS | 100 | FOOT | $31.73 | $35.20 | |
| 77 | 63100085 | TRAF BAR TERM T6 | 8 | EACH | $4,230.56 | $3,905.00 | |
| 78 | 63100167 | TR BAR TRM T1 SPL TAN | 8 | EACH | $3,278.68 | $3,460.00 | |
| 79 | 63200310 | GUARDRAIL REMOV | 720 | FOOT | $4.76 | $19.25 | |
| 80 | 66600105 | FUR ERECT ROW MARKERS | 12 | EACH | $215.98 | $250.00 | |
| 81 | 66700205 | PERM SURV MKRS T1 | 2 | EACH | $158.14 | $800.00 | |
| 82 | 67000400 | ENGR FIELD OFFICE A | 9 | CAL MO | $1,731.79 | $2,000.00 | |
| 83 | 67100100 | MOBILIZATION | 1 | L SUM | $190,751.88 | $215,064.67 | |
| 84 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $24,822.96 | $55,000.00 | |
| 85 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $14,302.53 | $1,000.00 | |
| 86 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $6,356.68 | $10,000.00 | |
| 87 | 70103815 | TR CONT SURVEILLANCE | 4 | CAL DA | $0.9900 | $800.00 | |
| 88 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $35,959.75 | $24,000.00 | |
| 89 | 70107005 | PAVT MK BLKOUT TAPE 5 | 495 | FOOT | $3.76 | $10.00 | |
| 90 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $83.52 | $250.00 | |
| 91 | 70300100 | SHORT TERM PAVT MKING | 116 | FOOT | $2.23 | $25.00 | |
| 92 | 70300150 | SHRT TRM PAVT MK REM | 21 | SQ FT | $5.16 | $100.00 | |
| 93 | 70300220 | TEMP PVT MK LINE 4 | 3,814 | FOOT | $1.02 | $2.00 | |
| 94 | 70400100 | TEMP CONC BARRIER | 462.5 | FOOT | $38.05 | $45.00 | |
| 95 | 70400200 | REL TEMP CONC BARRIER | 437.5 | FOOT | $6.88 | $7.00 | |
| 96 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $5,904.46 | $4,500.00 | |
| 97 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $896.49 | $2,500.00 | |
| 98 | 72501000 | TERMINAL MARKER - DA | 8 | EACH | $52.88 | $40.00 | |
| 99 | 78001110 | PAINT PVT MK LINE 4 | 3,814 | FOOT | $1.02 | $2.00 | |
| 100 | 78100100 | RAISED REFL PAVT MKR | 19 | EACH | $227.15 | $265.00 | |
| 101 | 78200006 | GRDRAIL REF TYPE B | 32 | EACH | $10.58 | $12.00 | |
| 102 | 78300200 | RAISED REF PVT MK REM | 19 | EACH | $9.93 | $150.00 | |
| 103 | 78300202 | PAVMT MRKG REM WTR BL | 413 | SQ FT | $9.02 | $25.00 |