(21)I-1
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K. E. Vas Company Low bidder | $53,069 | ||
| 2 | Stutz Excavating, Inc. | $56,533 | +6.5% | |
| 3 | L. W. Rouland Trucking Service, Inc. | $56,655 | +6.8% | |
| 4 | G. M. Sipes Construction, Inc. | $56,895 | +7.2% | |
| 5 | Phoenix Corporation of the Quad Cities | $58,257 | +9.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K. E. Vas Compa… | #2 Stutz Excavatin… | #3 L. W. Rouland T… | #4 G. M. Sipes Con… | #5 Phoenix Corpora… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 20800150 | TRENCH BACKFILL | 60 | CU YD | $50.00 | $45.00 | $80.00 | $50.00 | $50.00 | |
| 2 | 21301052 | EXPLOR TRENCH 52 | 50 | FOOT | $35.00 | $64.00 | $33.00 | $10.00 | $15.50 | |
| 3 | 44200204 | PAVT PATCH T3 17 | 48 | SQ YD | $318.00 | $335.00 | $540.00 | $750.00 | $450.00 | |
| 4 | 50800105 | REINFORCEMENT BARS | 31 | POUND | $10.00 | $4.00 | $35.00 | $20.00 | $6.00 | |
| 5 | 54002020 | EXPAN BOLTS 3/4 | 4 | EACH | $25.00 | $41.00 | $195.00 | $100.00 | $49.00 | |
| 6 | 54248510 | CONCRETE COLLAR | 0.3 | CU YD | $10,000.00 | $2,750.00 | $9,000.00 | $5,000.00 | $4,500.00 | |
| 7 | 60240215 | INLETS TB T1F CL | 1 | EACH | $2,500.00 | $3,800.00 | $1,500.00 | $3,500.00 | $2,400.00 | |
| 8 | 61101026 | STORM SEW PROT A 24 | 65 | FOOT | $233.00 | $376.00 | $180.00 | $75.00 | $250.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $2,000.00 | $3,500.00 | $3,320.00 | $2,500.00 | $3,500.00 | |
| 10 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $10,000.00 | $1,700.00 | $3,200.00 | $4,000.00 | $9,000.00 |