(69-6&7)BRR(69-8)BRR&BJR-1, SLP
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Freesen, a div of UCM, Inc. Low bidder | $578,512 | ||
| 2 | White Construction LLC | $721,997 | +24.8% | |
| 3 | Sangamo Construction Company | $771,468 | +33.4% | |
| 4 | Path Construction Company, Inc. | $944,260 | +63.2% | |
| 5 | County Contractors, Inc. | $1,186,171 | +105.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Freesen, a div … | #2 White Construct… | #3 Sangamo Constru… | #4 Path Constructi… | #5 County Contract… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0323818 | CLN & PT EXP RE-BAR | 36 | SQ FT | $262.16 | $99.00 | $260.99 | $50.00 | $171.00 | |
| 2 | X5030530 | FLOOR DRAIN EXTENSION | 4 | EACH | $1,892.12 | $1,140.00 | $1,371.36 | $1,200.00 | $1,500.00 | |
| 3 | Z0001899 | JACK & REM EX BEARING | 46 | EACH | $851.84 | $1,500.00 | $1,476.22 | $1,700.00 | $3,450.00 | |
| 4 | Z0012754 | STR REP CON DP = < 5 | 984 | SQ FT | $179.73 | $155.00 | $246.51 | $230.00 | $250.00 | |
| 5 | Z0021912 | SILICONE JT SEAL 2.5 | 220 | FOOT | $83.91 | $95.00 | $104.75 | $72.00 | $130.00 | |
| 6 | Z0021914 | SILICONE JT SEAL 2.75 | 132 | FOOT | $88.33 | $120.00 | $112.53 | $115.00 | $150.00 | |
| 7 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $7,295.36 | $7,000.00 | $4,187.17 | $10,000.00 | $10,000.00 | |
| 8 | Z0065702 | SLOPE WALL SPL | 196 | SQ YD | $158.56 | $180.00 | $152.80 | $125.00 | $265.00 | |
| 9 | Z0073200 | TEMP SHORING & CRIB | 1 | EACH | $16,891.95 | $7,700.00 | $9,178.23 | $22,000.00 | $9,500.00 | |
| 10 | 21400100 | GRADING & SHAP DITCH | 900 | FOOT | $12.46 | $10.00 | $9.78 | $30.00 | $10.00 | |
| 11 | 28100805 | STONE DUMP RIP CL A3 | 30 | TON | $243.41 | $130.00 | $116.51 | $215.00 | $140.00 | |
| 12 | 50102400 | CONC REM | 3.4 | CU YD | $1,372.31 | $2,950.00 | $3,168.19 | $5,000.00 | $3,800.00 | |
| 13 | 50104650 | SLOPE WALL REMOV | 196 | SQ YD | $55.17 | $175.00 | $90.94 | $125.00 | $90.00 | |
| 14 | 50300225 | CONC STRUCT | 2.1 | CU YD | $4,784.84 | $2,785.00 | $7,309.37 | $11,000.00 | $4,500.00 | |
| 15 | 50500405 | F & E STRUCT STEEL | 11,060 | POUND | $5.18 | $5.50 | $4.63 | $7.00 | $18.00 | |
| 16 | 50800205 | REINF BARS, EPOXY CTD | 380 | POUND | $4.22 | $4.00 | $5.34 | $6.00 | $3.00 | |
| 17 | 52100010 | ELAST BEARING ASSY T1 | 46 | EACH | $1,052.92 | $1,090.00 | $1,734.03 | $2,500.00 | $3,750.00 | |
| 18 | 52100520 | ANCHOR BOLTS 1 | 92 | EACH | $198.01 | $110.00 | $118.71 | $80.00 | $85.00 | |
| 19 | 59300100 | CONTR LOW-STRENG MATL | 65 | CU YD | $305.19 | $325.00 | $264.86 | $350.00 | $265.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $8,680.42 | $43,319.84 | $45,516.61 | $55,000.00 | $40,000.00 | |
| 21 | 70100420 | TRAF CONT-PROT 701411 | 5 | EACH | $1,575.00 | $1,500.00 | $3,649.28 | $300.00 | $2,900.00 | |
| 22 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $6,713.66 | $7,500.00 | $15,532.00 | $1,260.00 | $4,000.00 | |
| 23 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $47,386.50 | $140,500.00 | $68,224.18 | $165,000.00 | $140,000.00 |