(6) CR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K. E. Vas Company Low bidder | $129,397 | ||
| 2 | L. W. Rouland Trucking Service, Inc. | $144,144 | +11.4% | |
| 3 | G. M. Sipes Construction, Inc. | $154,010 | +19.0% | |
| 4 | Prado Construction | $158,972 | +22.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K. E. Vas Compa… | #2 L. W. Rouland T… | #3 G. M. Sipes Con… | #4 Prado Construct… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 20800150 | TRENCH BACKFILL | 300 | CU YD | $51.00 | $40.00 | $50.00 | $132.12 | |
| 2 | 44201377 | CL C PATCH T2 12 | 88 | SQ YD | $435.00 | $575.00 | $450.00 | $267.32 | |
| 3 | 44213204 | TIE BARS 3/4 | 96 | EACH | $10.00 | $16.00 | $5.00 | $20.10 | |
| 4 | 50104400 | CONC HDWL REM | 10 | EACH | $500.00 | $300.00 | $700.00 | $422.94 | |
| 5 | 50105220 | PIPE CULVERT REMOV | 269 | FOOT | $20.00 | $10.00 | $35.00 | $50.52 | |
| 6 | 542A0220 | P CUL CL A 1 15 | 109 | FOOT | $173.00 | $130.00 | $135.00 | $75.40 | |
| 7 | 542A0223 | P CUL CL A 1 18 | 50 | FOOT | $193.00 | $140.00 | $145.00 | $81.98 | |
| 8 | 542A0229 | P CUL CL A 1 24 | 110 | FOOT | $187.00 | $150.00 | $155.00 | $129.64 | |
| 9 | 54213660 | PRC FLAR END SEC 15 | 4 | EACH | $700.00 | $1,100.00 | $1,500.00 | $970.02 | |
| 10 | 54213663 | PRC FLAR END SEC 18 | 2 | EACH | $800.00 | $1,200.00 | $1,750.00 | $1,128.58 | |
| 11 | 54213669 | PRC FLAR END SEC 24 | 4 | EACH | $1,000.00 | $1,500.00 | $2,000.00 | $1,307.96 | |
| 12 | 67100100 | MOBILIZATION | 1 | L SUM | $5,000.00 | $9,500.00 | $9,000.00 | $12,950.04 | |
| 13 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $2,000.00 | $14,348.00 | $17,000.00 | $25,165.78 |