(135)RS-7
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Truman L. Flatt & Sons Co., Inc. Low bidder | $288,657 | ||
| 2 | P. H. Broughton & Sons, Inc. | $317,854 | +10.1% | |
| 3 | Illinois Valley Paving, a div of UCM, Inc. | $357,889 | +24.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Truman L. Flatt… | #2 P. H. Broughton… | #3 Illinois Valley… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2020110 | GRADING & SHAP SHLDRS | 10 | UNIT | $466.86 | $516.87 | $477.55 | |
| 2 | X4401198 | HMA SURF REM VAR DP | 7,089 | SQ YD | $2.44 | $3.45 | $4.38 | |
| 3 | Z0005300 | BOX CUL TO BE CLEANED | 2 | EACH | $1,134.00 | $2,696.64 | $4,109.42 | |
| 4 | Z0033700 | LONG JOINT SEALANT | 2,774 | FOOT | $4.06 | $4.37 | $5.00 | |
| 5 | 20800150 | TRENCH BACKFILL | 80 | CU YD | $33.36 | $26.89 | $70.02 | |
| 6 | 21400100 | GRADING & SHAP DITCH | 1,792 | FOOT | $12.48 | $10.75 | $10.34 | |
| 7 | 25000200 | SEEDING CL 2 | 0.25 | ACRE | $7,717.52 | $5,377.04 | $8,085.00 | |
| 8 | 25000400 | NITROGEN FERT NUTR | 4 | POUND | $1.21 | $7.53 | $1.27 | |
| 9 | 25000500 | PHOSPHORUS FERT NUTR | 4 | POUND | $1.21 | $7.53 | $1.27 | |
| 10 | 25000600 | POTASSIUM FERT NUTR | 4 | POUND | $1.21 | $7.53 | $1.27 | |
| 11 | 25000700 | AGR GROUND LIMESTONE | 4 | TON | $152.25 | $2,903.61 | $159.50 | |
| 12 | 25100125 | MULCH METHOD 3 | 0.25 | ACRE | $7,297.52 | $7,635.40 | $7,645.00 | |
| 13 | 28000305 | TEMP DITCH CHECKS | 70 | FOOT | $10.88 | $8.60 | $26.40 | |
| 14 | 28000500 | INLET & PIPE PROTECT | 10 | EACH | $140.00 | $150.56 | $481.18 | |
| 15 | 35800100 | PREPARATION OF BASE | 72 | SQ YD | $5.85 | $12.75 | $18.77 | |
| 16 | 40600290 | BIT MATLS TACK CT | 3,245 | POUND | $0.5600 | $1.00 | $2.21 | |
| 17 | 40600982 | HMA SURF REM BUTT JT | 1,554 | SQ YD | $10.59 | $4.27 | $16.25 | |
| 18 | 40600990 | TEMPORARY RAMP | 33 | SQ YD | $22.81 | $18.95 | $46.96 | |
| 19 | 40604050 | HMA SC IL-9.5 C N50 | 860 | TON | $91.80 | $101.21 | $117.11 | |
| 20 | 40800029 | BIT MATLS TACK CT | 700 | POUND | $0.5600 | $1.00 | $7.39 | |
| 21 | 40800050 | INCIDENTAL HMA SURF | 217 | TON | $220.16 | $173.75 | $206.94 | |
| 22 | 44000200 | DRIVE PAVEMENT REM | 95 | SQ YD | $10.34 | $21.51 | $45.59 | |
| 23 | 48102100 | AGG WEDGE SHLD TYPE B | 89 | TON | $53.39 | $46.50 | $83.73 | |
| 24 | 50104400 | CONC HDWL REM | 3 | EACH | $307.46 | $1,021.64 | $762.42 | |
| 25 | 50105220 | PIPE CULVERT REMOV | 375 | FOOT | $20.14 | $24.73 | $11.00 | |
| 26 | 542D0220 | P CUL CL D 1 15 | 550 | FOOT | $51.62 | $59.15 | $33.43 | |
| 27 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,229.90 | $2,796.99 | $2,407.88 | |
| 28 | 67100100 | MOBILIZATION | 1 | L SUM | $5,578.99 | $13,504.15 | $10,719.06 | |
| 29 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $5,298.25 | $5,305.98 | $6,514.31 | |
| 30 | 70300100 | SHORT TERM PAVT MKING | 561 | FOOT | $0.4300 | $0.8100 | $2.20 | |
| 31 | 70300150 | SHRT TRM PAVT MK REM | 94 | SQ FT | $9.90 | $8.47 | $8.70 | |
| 32 | 78001120 | PAINT PVT MK LINE 5 | 6,867 | FOOT | $0.5500 | $0.5500 | $0.5700 | |
| 33 | 78100100 | RAISED REFL PAVT MKR | 36 | EACH | $68.78 | $70.44 | $72.05 | |
| 34 | 78300200 | RAISED REF PVT MK REM | 36 | EACH | $20.69 | $32.10 | $46.04 |