(22)BDR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Freesen, a div of UCM, Inc. Low bidder | $434,690 | ||
| 2 | Stark Excavating, Inc. | $461,400 | +6.1% | |
| 3 | Sangamo Construction Company | $465,612 | +7.1% | |
| 4 | White Construction LLC | $478,445 | +10.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Freesen, a div … | #2 Stark Excavatin… | #3 Sangamo Constru… | #4 White Construct… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327980 | PAVMT MRKG REM WTR BL | 469 | SQ FT | $5.50 | $9.25 | $12.79 | $12.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $39,765.00 | $14,000.00 | $30,853.93 | $13,132.09 | |
| 3 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $3,080.00 | $1,400.00 | $2,771.02 | $1,330.50 | |
| 4 | Z0012130 | BR DECK SCAR 3/4 | 1,545 | SQ YD | $46.32 | $57.00 | $52.22 | $54.50 | |
| 5 | Z0012164 | BR DK MIC C OVL 2 1/2 | 1,545 | SQ YD | $97.12 | $106.00 | $97.11 | $106.00 | |
| 6 | Z0016001 | DECK SLAB REP (FD-T1) | 10 | SQ YD | $1,197.39 | $2,355.00 | $1,100.82 | $2,075.00 | |
| 7 | Z0018051 | DRAINAGE SCUPPERS ADJ | 2 | EACH | $5,127.35 | $4,750.00 | $3,525.04 | $3,350.00 | |
| 8 | Z0041895 | POLYMER CONCRETE | 8.5 | CU FT | $1,162.69 | $1,180.00 | $998.40 | $1,300.00 | |
| 9 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $6,994.12 | $3,000.00 | $3,615.96 | $3,735.00 | |
| 10 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 11 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 12 | 28100205 | STONE RIPRAP CL A3 | 20 | TON | $110.27 | $140.00 | $108.68 | $60.00 | |
| 13 | 35501314 | HMA BASE CSE 7 1/2 | 196 | SQ YD | $76.08 | $81.25 | $116.38 | $109.20 | |
| 14 | 40600290 | BIT MATLS TACK CT | 217 | POUND | $7.06 | $7.50 | $3.20 | $3.00 | |
| 15 | 40600982 | HMA SURF REM BUTT JT | 529 | SQ YD | $15.38 | $16.50 | $20.68 | $19.40 | |
| 16 | 40600985 | PCC SURF REM BUTT JT | 31 | SQ YD | $62.85 | $66.50 | $20.68 | $19.40 | |
| 17 | 40600990 | TEMPORARY RAMP | 69 | SQ YD | $15.54 | $46.00 | $45.86 | $140.00 | |
| 18 | 40604060 | HMA SC IL-9.5 D N50 | 52 | TON | $269.85 | $290.00 | $292.35 | $274.31 | |
| 19 | 42001300 | PROTECTIVE COAT | 1,545 | SQ YD | $3.04 | $3.00 | $3.28 | $3.00 | |
| 20 | 44004250 | PAVED SHLD REMOVAL | 196 | SQ YD | $39.32 | $41.50 | $30.37 | $30.00 | |
| 21 | 48203100 | HMA SHOULDERS | 16.5 | TON | $187.74 | $200.50 | $292.35 | $274.31 | |
| 22 | 50300260 | BR DECK GROOVING | 1,451 | SQ YD | $10.91 | $11.50 | $9.21 | $7.35 | |
| 23 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,558.68 | $1,950.00 | $1,616.59 | $2,500.00 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $19,000.03 | $9,963.50 | $27,471.12 | $28,232.72 | |
| 25 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $1.10 | $17,500.00 | $14,658.48 | $16,638.12 | |
| 26 | 70107025 | CHANGEABLE MESSAGE SN | 30 | CAL DA | $138.60 | $94.50 | $189.91 | $90.00 | |
| 27 | 78009005 | MOD URETH PM LINE 5 | 4,870 | FOOT | $1.43 | $2.40 | $3.05 | $2.86 |