(75-1-1)RS-2,BRR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $4,455,235 | ||
| 2 | CHESTER BROSS CONSTRUCTION COMPANY | $4,460,748 | +0.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… | #2 CHESTER BROSS C… |
|---|---|---|---|---|---|---|---|
| 1 | X0320157 | CLEAN UNDERDR OUTLET | 73 | EACH | $105.00 | $255.00 | |
| 2 | X0322279 | OUTLET MARKER | 73 | EACH | $33.60 | $41.30 | |
| 3 | X2503000 | MAINTENANCE MOWING | 40.5 | ACRE | $89.25 | $100.00 | |
| 4 | X4820110 | HMA SHLD REM REPL SPL | 500 | SQ YD | $147.71 | $86.00 | |
| 5 | X6024205 | MED INLET (604101) SP | 3 | EACH | $6,300.00 | $9,700.00 | |
| 6 | X6350120 | DELINEATOR REMOVAL | 100 | EACH | $20.33 | $13.00 | |
| 7 | X6430120 | REM IMP ATTEN NO SALV | 4 | EACH | $928.85 | $645.00 | |
| 8 | X6431210 | REM REPL ATTEN BASE | 4 | EACH | $4,734.98 | $8,400.00 | |
| 9 | X7015005 | CHANGEABLE MESSAGE SN | 78 | CAL DA | $90.43 | $83.85 | |
| 10 | X7040650 | REM TEMP CONC BARRIER | 150 | FOOT | $27.07 | $82.50 | |
| 11 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $7,462.67 | $900.00 | |
| 12 | X7830072 | GRV RCSD PVT MRKG 6 | 57,519 | FOOT | $0.3300 | $0.4000 | |
| 13 | X7830076 | GRV RCSD PVT MRKG 9 | 1,683 | FOOT | $0.6500 | $0.8000 | |
| 14 | X7830078 | GRV RCSD PVT MRKG 13 | 308 | FOOT | $2.63 | $3.25 | |
| 15 | Z0001800 | APPROACH SL REP (PD) | 13.2 | SQ YD | $1,360.48 | $2,350.00 | |
| 16 | Z0012754 | STR REP CON DP = < 5 | 157.5 | SQ FT | $340.02 | $600.00 | |
| 17 | Z0012755 | STR REP CON DP OVER 5 | 3 | SQ FT | $1,212.09 | $625.50 | |
| 18 | Z0016200 | DECK SLAB REP (PART) | 0.9 | SQ YD | $5,078.09 | $3,550.00 | |
| 19 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $22,777.56 | $1,419.00 | |
| 20 | Z0033700 | LONG JOINT SEALANT | 29,102 | FOOT | $2.90 | $3.10 | |
| 21 | Z0034105 | MATL TRANSFER DEVICE | 16,332 | TON | $3.65 | $3.60 | |
| 22 | Z0065796 | RIPRAP SLURRY | 218 | SQ YD | $28.35 | $51.60 | |
| 23 | Z0076600 | TRAINEES | 2,500 | HOUR | $0.8000 | $0.8000 | |
| 24 | Z0076604 | TRAINEES TPG | 2,500 | HOUR | $15.00 | $15.00 | |
| 25 | 21400100 | GRADING & SHAP DITCH | 269 | FOOT | $15.65 | $32.25 | |
| 26 | 28100705 | STONE DUMP RIP CL A3 | 432 | SQ YD | $44.10 | $51.60 | |
| 27 | 28200200 | FILTER FABRIC | 432 | SQ YD | $2.10 | $4.50 | |
| 28 | 40600290 | BIT MATLS TACK CT | 74,062 | POUND | $1.32 | $0.3100 | |
| 29 | 40600982 | HMA SURF REM BUTT JT | 765 | SQ YD | $8.71 | $20.15 | |
| 30 | 40600990 | TEMPORARY RAMP | 163 | SQ YD | $10.46 | $1.00 | |
| 31 | 40603240 | P HMA BC IL19.0 N90 | 9,763 | TON | $105.38 | $98.40 | |
| 32 | 40603570 | P HMA SC "E" N90 | 6,569 | TON | $124.88 | $120.80 | |
| 33 | 40800050 | INCIDENTAL HMA SURF | 167 | TON | $146.10 | $150.65 | |
| 34 | 44000155 | HMA SURF REM 1 1/2 | 49,312 | SQ YD | $3.70 | $3.00 | |
| 35 | 44000162 | HMA SURF REM 3 1/4 | 77,480 | SQ YD | $5.89 | $3.35 | |
| 36 | 44201839 | CL D PATCH T2 16 | 77 | SQ YD | $401.42 | $300.00 | |
| 37 | 48102100 | AGG WEDGE SHLD TYPE B | 2,465 | TON | $36.95 | $41.15 | |
| 38 | 48203100 | HMA SHOULDERS | 5,357 | TON | $90.52 | $88.25 | |
| 39 | 50102400 | CONC REM | 0.8 | CU YD | $5,423.66 | $12,900.00 | |
| 40 | 50105220 | PIPE CULVERT REMOV | 30 | FOOT | $10.50 | $51.60 | |
| 41 | 50300225 | CONC STRUCT | 19.3 | CU YD | $1,732.08 | $3,550.00 | |
| 42 | 50800205 | REINF BARS, EPOXY CTD | 1,880 | POUND | $5.19 | $3.25 | |
| 43 | 54002020 | EXPAN BOLTS 3/4 | 8 | EACH | $78.75 | $142.00 | |
| 44 | 54213447 | END SECTIONS 12 | 2 | EACH | $525.00 | $1,225.50 | |
| 45 | 54248510 | CONCRETE COLLAR | 0.3 | CU YD | $7,192.50 | $12,255.00 | |
| 46 | 60100945 | PIPE DRAINS 12 | 30 | FOOT | $52.50 | $116.00 | |
| 47 | 63000001 | SPBGR TY A 6FT POSTS | 2,300 | FOOT | $23.99 | $35.35 | |
| 48 | 63100045 | TRAF BAR TERM T2 | 4 | EACH | $1,375.50 | $2,000.00 | |
| 49 | 63100085 | TRAF BAR TERM T6 | 8 | EACH | $3,244.50 | $4,785.00 | |
| 50 | 63100167 | TR BAR TRM T1 SPL TAN | 12 | EACH | $3,102.75 | $4,575.00 | |
| 51 | 63200310 | GUARDRAIL REMOV | 3,300 | FOOT | $7.98 | $11.80 | |
| 52 | 63500105 | DELINEATORS | 293 | EACH | $60.17 | $83.85 | |
| 53 | 64200116 | SHOULDER RUM STRIP 16 | 57,744 | FOOT | $0.5000 | $0.3300 | |
| 54 | 64300450 | IMP ATTEN NRD TL3 | 4 | EACH | $7,169.09 | $7,100.00 | |
| 55 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,411.54 | $1,500.00 | |
| 56 | 67100100 | MOBILIZATION | 1 | L SUM | $181,392.66 | $512,000.00 | |
| 57 | 70100420 | TRAF CONT-PROT 701411 | 3 | EACH | $4,319.99 | $645.00 | |
| 58 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $5,241.74 | $645.00 | |
| 59 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $27,447.34 | $11,610.00 | |
| 60 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $65,471.81 | $21,285.00 | |
| 61 | 70100820 | TRAF CONT-PROT 701451 | 1 | L SUM | $18,135.25 | $645.00 | |
| 62 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $11,246.10 | $645.00 | |
| 63 | 70300100 | SHORT TERM PAVT MKING | 3,659 | FOOT | $1.66 | $2.25 | |
| 64 | 70300150 | SHRT TRM PAVT MK REM | 1,220 | SQ FT | $7.12 | $4.30 | |
| 65 | 72000100 | SIGN PANEL T1 | 15.3 | SQ FT | $38.27 | $64.50 | |
| 66 | 72000200 | SIGN PANEL T2 | 36 | SQ FT | $40.32 | $64.50 | |
| 67 | 72400310 | REMOV SIGN PANEL T1 | 16 | SQ FT | $13.13 | $19.35 | |
| 68 | 72501000 | TERMINAL MARKER - DA | 12 | EACH | $42.00 | $58.00 | |
| 69 | 73000100 | WOOD SIN SUPPORT | 48 | FOOT | $30.08 | $51.60 | |
| 70 | 78004220 | PREF PL PM TB INL L5 | 6,265 | FOOT | $3.66 | $4.50 | |
| 71 | 78009005 | MOD URETH PM LINE 5 | 58,916 | FOOT | $0.7600 | $0.9300 | |
| 72 | 78009008 | MOD URETH PM LINE 8 | 1,683 | FOOT | $1.22 | $1.50 | |
| 73 | 78009012 | MOD URETH PM LINE 12 | 308 | FOOT | $1.83 | $2.25 | |
| 74 | 78100100 | RAISED REFL PAVT MKR | 474 | EACH | $28.57 | $35.10 | |
| 75 | 78200005 | GRDRAIL REF TYPE A | 46 | EACH | $8.93 | $11.60 | |
| 76 | 78300200 | RAISED REF PVT MK REM | 474 | EACH | $21.39 | $25.00 |