(102RS-10, 119RS-3)SW,1
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Diamond Construction Company Low bidder | $4,996,176 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Diamond Constru… |
|---|---|---|---|---|---|---|
| 1 | X2020060 | EXC & GR EX SHLD SPL | 43 | UNIT | $1,500.00 | |
| 2 | X4240420 | PC CONC SIDEWALK 4 SP | 6,200 | SQ FT | $15.75 | |
| 3 | X4401198 | HMA SURF REM VAR DP | 7,640 | SQ YD | $3.50 | |
| 4 | X4811900 | AGGREGATE SHLDS SPL | 282 | TON | $99.75 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $36,750.00 | |
| 6 | Z0034105 | MATL TRANSFER DEVICE | 10,543 | TON | $6.00 | |
| 7 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $2,100.00 | |
| 8 | Z0076600 | TRAINEES | 2,000 | HOUR | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 2,000 | HOUR | $15.00 | |
| 10 | 21400100 | GRADING & SHAP DITCH | 109 | FOOT | $19.50 | |
| 11 | 35800100 | PREPARATION OF BASE | 647 | SQ YD | $10.00 | |
| 12 | 40200800 | AGG SURF CSE B | 65 | TON | $50.40 | |
| 13 | 40600290 | BIT MATLS TACK CT | 66,827 | POUND | $2.00 | |
| 14 | 40600370 | LONG JOINT SEALANT | 42,858 | FOOT | $3.10 | |
| 15 | 40600982 | HMA SURF REM BUTT JT | 3,712 | SQ YD | $50.00 | |
| 16 | 40600990 | TEMPORARY RAMP | 120 | SQ YD | $10.00 | |
| 17 | 40602965 | HMA BC IL-9.5FG N50 | 8,249 | TON | $135.00 | |
| 18 | 40604050 | HMA SC IL-9.5 C N50 | 10,543 | TON | $125.00 | |
| 19 | 40800050 | INCIDENTAL HMA SURF | 684 | TON | $280.00 | |
| 20 | 42400800 | DETECTABLE WARNINGS | 607 | SQ FT | $54.65 | |
| 21 | 44000155 | HMA SURF REM 1 1/2 | 19,085 | SQ YD | $3.50 | |
| 22 | 44000157 | HMA SURF REM 2 | 91,337 | SQ YD | $3.50 | |
| 23 | 44000160 | HMA SURF REM 2 3/4 | 8,235 | SQ YD | $3.50 | |
| 24 | 44000400 | GUTTER REM | 94 | FOOT | $54.65 | |
| 25 | 44000500 | COMB CURB GUTTER REM | 219 | FOOT | $54.65 | |
| 26 | 44000600 | SIDEWALK REM | 4,696 | SQ FT | $4.25 | |
| 27 | 48102100 | AGG WEDGE SHLD TYPE B | 2,084 | TON | $38.50 | |
| 28 | 48203023 | HMA SHOULDERS 6 1/2 | 1,895 | SQ YD | $75.00 | |
| 29 | 48203100 | HMA SHOULDERS | 216 | TON | $100.00 | |
| 30 | 50105220 | PIPE CULVERT REMOV | 21 | FOOT | $82.00 | |
| 31 | 542A0217 | P CUL CL A 1 12 | 88 | FOOT | $184.00 | |
| 32 | 60255500 | MAN ADJUST | 5 | EACH | $1,050.00 | |
| 33 | 60300105 | FR & GRATES ADJUST | 3 | EACH | $1,315.00 | |
| 34 | 60602500 | CONC GUTTER TA | 94 | FOOT | $155.50 | |
| 35 | 60605000 | COMB CC&G TB6.24 | 219 | FOOT | $142.00 | |
| 36 | 63000007 | SPBGR TY B 6FT POSTS | 2,650 | FOOT | $32.00 | |
| 37 | 63100167 | TR BAR TRM T1 SPL TAN | 36 | EACH | $3,420.00 | |
| 38 | 63200310 | GUARDRAIL REMOV | 4,179 | FOOT | $4.20 | |
| 39 | 66900200 | NON SPL WASTE DISPOSL | 72 | CU YD | $315.00 | |
| 40 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,260.00 | |
| 41 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,310.00 | |
| 42 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,310.00 | |
| 43 | 66901006 | REG SUB MON | 8 | CAL DA | $1,207.50 | |
| 44 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,000.00 | |
| 45 | 67100100 | MOBILIZATION | 1 | L SUM | $158,500.00 | |
| 46 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $50,000.00 | |
| 47 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $115,000.00 | |
| 48 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $10,000.00 | |
| 49 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1,500.00 | |
| 50 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $20,000.00 | |
| 51 | 70300100 | SHORT TERM PAVT MKING | 17,495 | FOOT | $0.7500 | |
| 52 | 70300150 | SHRT TRM PAVT MK REM | 1,458 | SQ FT | $3.00 | |
| 53 | 70300231 | TEMP PVT MK LINE 5 - PAINT | 113,246 | FOOT | $0.0100 | |
| 54 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 2,965 | FOOT | $0.0100 | |
| 55 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 34 | FOOT | $0.0100 | |
| 56 | 72501000 | TERMINAL MARKER - DA | 36 | EACH | $57.75 | |
| 57 | 78000300 | THPL PVT MK LINE 5 | 20,707 | FOOT | $1.25 | |
| 58 | 78000400 | THPL PVT MK LINE 6 | 2,965 | FOOT | $1.50 | |
| 59 | 78001120 | PAINT PVT MK LINE 5 | 92,539 | FOOT | $0.1700 | |
| 60 | 78004280 | PREF PL PM TB INL L24 | 34 | FOOT | $80.00 | |
| 61 | 78100100 | RAISED REFL PAVT MKR | 539 | EACH | $38.00 | |
| 62 | 78200005 | GRDRAIL REF TYPE A | 68 | EACH | $15.75 | |
| 63 | 78300200 | RAISED REF PVT MK REM | 539 | EACH | $10.00 |