Bid tab 72878

Let Jan 17, 2025 · District 6 · Pike

‹ Jan 2025 results

(75-6)CJS

Let date
Friday, January 17, 2025
Contract
72878 · job page
District
District 6
County
Pike
Highway
Limits
6.3 miles of crack and joint seal on I-72 from 0.4 miles east of the US 54/IL 107 interchange to the Scott County line.
Classification
·
Project number

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Freehill Asphalt, Inc. Low bidder $83,522
2 SKC Construction, Inc. $98,607 +18.1%
3 Complete Asphalt Service Co. $99,968 +19.7%
4 Denler, Inc. $105,897 +26.8%

Bid tab: unit prices 4 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Freehill Asphal…#2 SKC Constructio…#3 Complete Asphal…#4 Denler, Inc.
1X7010216 TRAF CONT & PROT SPL1L SUM $25,000.00 $22,538.00 $25,000.00 $20,000.00
245100200 CRACK FILLING34,548POUND $1.50 $1.82 $1.84 $2.22
367100100 MOBILIZATION1L SUM $4,500.00 $8,000.00 $5,900.00 $7,000.00
470107025 CHANGEABLE MESSAGE SN44CAL DA $50.00 $118.00 $125.00 $50.00