28CJS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Complete Asphalt Service Co. Low bidder | $22,444 | ||
| 2 | Freehill Asphalt, Inc. | $28,736 | +28.0% | |
| 3 | Kinney Contractors, Inc. | $34,950 | +55.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Complete Asphal… | #2 Freehill Asphal… | #3 Kinney Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | 45100100 | CRACK ROUTING (PAVT) | 2,500 | FOOT | $0.1000 | $0.1000 | $0.0100 | |
| 2 | 45100200 | CRACK FILLING | 7,609 | POUND | $1.55 | $3.31 | $2.75 | |
| 3 | 67100100 | MOBILIZATION | 1 | L SUM | $1,300.00 | $1,700.00 | $2,000.00 | |
| 4 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $9,000.00 | $1,500.00 | $11,900.00 | |
| 5 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $100.00 | $100.00 |