(84-3-1,2)CJS
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $210,848 | ||
| 2 | Freehill Asphalt, Inc. | $237,743 | +12.8% | |
| 3 | Complete Asphalt Service Co. | $247,853 | +17.6% | |
| 4 | SKC Construction, Inc. | $250,602 | +18.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 Freehill Asphal… | #3 Complete Asphal… | #4 SKC Constructio… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $48,000.00 | $80,000.00 | $40,000.00 | $82,290.00 | |
| 2 | 45100100 | CRACK ROUTING (PAVT) | 11,034 | FOOT | $0.1000 | $0.1000 | $0.1000 | $0.1000 | |
| 3 | 45100200 | CRACK FILLING | 54,878.5 | POUND | $2.10 | $1.73 | $2.88 | $2.40 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $12,000.00 | $14,000.00 | $14,000.00 | $12,000.00 | |
| 5 | 70107025 | CHANGEABLE MESSAGE SN | 140 | CAL DA | $125.00 | $55.00 | $105.00 | $100.00 | |
| 6 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $17,000.00 | $40,000.00 | $20,000.00 | $9,500.00 |