(240B)BR-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stark Excavating, Inc. Low bidder | $414,045 | ||
| 2 | Sangamo Construction Company | $515,950 | +24.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stark Excavatin… | #2 Sangamo Constru… |
|---|---|---|---|---|---|---|---|
| 1 | X5010010 | REM EX PPC DECK BEAMS | 795 | SQ FT | $80.00 | $100.32 | |
| 2 | X5030275 | CONC WEARING SURF REM | 119 | SQ YD | $0.0100 | $206.92 | |
| 3 | X5030305 | CONC WEARING SURF 5 | 119 | SQ YD | $465.00 | $280.29 | |
| 4 | X5091742 | REM & RE-E EX BR RAIL | 265 | FOOT | $150.00 | $152.32 | |
| 5 | X7200203 | DETOUR SIGNING | 1 | L SUM | $10,000.00 | $11,086.17 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $1,300.00 | $3,840.24 | |
| 7 | 50300300 | PROTECTIVE COAT | 119 | SQ YD | $6.00 | $4.89 | |
| 8 | 50400405 | P P CONC DK BM 21 DP | 795 | SQ FT | $220.00 | $302.77 | |
| 9 | 50800205 | REINF BARS, EPOXY CTD | 1,530 | POUND | $4.00 | $3.51 | |
| 10 | 50800530 | MECHANICAL SPLICERS | 268 | EACH | $40.00 | $58.58 | |
| 11 | 53212754 | STR REP CON DP = < 5 | 102 | SQ FT | $185.00 | $200.12 | |
| 12 | 67000500 | ENGR FIELD OFFICE B | 3 | CAL MO | $2,100.00 | $2,663.78 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $24,825.00 | $30,441.06 | |
| 14 | 70107025 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $115.00 | $123.44 |