D5 TREE REM 2024-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Endrizzi Contracting, Inc Low bidder | $305,750 | ||
| 2 | Mosley Construction 1, LLC | $385,000 | +25.9% | |
| 3 | CSD Environmental Services, Inc. | $461,250 | +50.9% |
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Endrizzi Contracting, Inc Low bidder | $305,750 | ||
| 2 | Mosley Construction 1, LLC | $385,000 | +25.9% | |
| 3 | CSD Environmental Services, Inc. | $461,250 | +50.9% |