CM2023-1
- Let date
- Friday, July 15, 2022
- Contract
- 70F89 · job page
- District
- District 5
- County
- Dewitt, Mclean
- Highway
- Limits
- 0.282 Mile of Standard Overlay at Median Turnaround at Mclean I Dewitt County Line South of Heyworth and at Quest Drive Frontage Road South of Bloomington.
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Rowe Construction, a div of UCM, Inc. Low bidder | $242,701 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Rowe Constructi… |
|---|---|---|---|---|---|---|
| 1 | X4400196 | HMA SURF REM SPL | 732 | SQ YD | $20.51 | |
| 2 | Z0038119 | PCC SUR REM 1 1/2 | 54 | SQ YD | $20.75 | |
| 3 | 35800100 | PREPARATION OF BASE | 261 | SQ YD | $12.63 | |
| 4 | 35800200 | AGG BASE REPAIR | 14 | TON | $185.61 | |
| 5 | 40600275 | BIT MATLS PR CT | 216 | POUND | $5.05 | |
| 6 | 40600290 | BIT MATLS TACK CT | 2,456 | POUND | $5.02 | |
| 7 | 40600370 | LONG JOINT SEALANT | 1,252 | FOOT | $9.49 | |
| 8 | 40600900 | HMA BC HM N50 | 17 | TON | $281.29 | |
| 9 | 40600990 | TEMPORARY RAMP | 14 | SQ YD | $63.66 | |
| 10 | 40604050 | HMA SC IL-9.5 C N50 | 378 | TON | $140.00 | |
| 11 | 40800029 | BIT MATLS TACK CT | 354 | POUND | $0.8500 | |
| 12 | 40800050 | INCIDENTAL HMA SURF | 67 | TON | $300.00 | |
| 13 | 44000155 | HMA SURF REM 1 1/2 | 4,649 | SQ YD | $6.73 | |
| 14 | 44000165 | HMA SURF REM 4 | 304 | SQ YD | $42.15 | |
| 15 | 44004250 | PAVED SHLD REMOVAL | 96 | SQ YD | $35.84 | |
| 16 | 48102100 | AGG WEDGE SHLD TYPE B | 47 | TON | $159.20 | |
| 17 | 48203100 | HMA SHOULDERS | 130 | TON | $250.00 | |
| 18 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | |
| 19 | 70100205 | TRAF CONT-PROT 701401 | 2 | EACH | $4,071.66 | |
| 20 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $6,050.52 | |
| 21 | 70300100 | SHORT TERM PAVT MKING | 232 | FOOT | $1.96 | |
| 22 | 70300150 | SHRT TRM PAVT MK REM | 38 | SQ FT | $5.97 | |
| 23 | 78001110 | PAINT PVT MK LINE 4 | 2,968 | FOOT | $1.34 |